Flashcards · YAC11 · A Level Topic 2.5
Standard costing (A Level) flashcards
10 cards on A Level Topic 2.5. Pick a subtopic or study them all.
Study mode needs JavaScript. Every card is listed below, so you can still cover the answers and test yourself.
Choose your cards
Session complete
Worth another look:
All 10 cards
For a quick read-through or printing. Cover the right-hand side to test yourself.
Topic 2.5: Standard costing
- Ideal, attainable and basic standards
- Ideal: perfect conditions, no waste or idle time. Attainable: allows normal waste and idle time; demanding but achievable. Basic: kept unchanged for a long period to show trends.
- Standard 4 kg at 5 per unit. 500 units made using 2,100 kg costing 10,080. Material variances?
- Actual price 4.80; SQ 2,000 kg. Price (5 − 4.80) × 2,100 = 420 F. Usage (2,000 − 2,100) × 5 = 500 A. Total 10,000 − 10,080 = 80 A.
- Standard hours 900, actual hours 870, standard rate 20, actual rate 21. Labour variances?
- Rate (20 − 21) × 870 = 870 A. Efficiency (900 − 870) × 20 = 600 F. Total 18,000 − 18,270 = 270 A.
- Standard fixed overhead 9 per unit; output 2,400 units; actual fixed overhead 22,500. Total fixed overhead variance?
- Absorbed 2,400 × 9 = 21,600. 21,600 − 22,500 = 900 A (under-absorbed).
- Standard variable overhead 1.50 per unit; output 6,000; actual variable overhead 8,700. Variance?
- 6,000 × 1.50 = 9,000. 9,000 − 8,700 = 300 F.
- Cheaper, lower-grade material is bought. Which variances can it create?
- Material price F, material usage A and labour efficiency A. One manager's favourable variance can cause another's adverse one.
- Management by exception
- Managers investigate only significant variances, outside a set tolerance, favourable as well as adverse, and watch trends.
- Where are actual material prices, quantities used and hours worked collected from?
- Prices: purchase invoices. Quantities used: stores requisitions and inventory records. Hours: clock cards, time sheets and job cards.
- Can a total variance of zero still need investigating?
- Yes. Large favourable and adverse sub-variances can cancel, for example cheap material (price F) causing waste (usage A).
- A price variance of 600 A arose on 3,000 kg bought at 4.20 per kg. Standard price?
- 600 ÷ 3,000 = 0.20 above standard, so the standard price is 4.20 − 0.20 = 4.00.