Cambridge A Level Business (9609): Budgets – Revision Notes

Condensed recall for 9609 section 5.5 Budgets: purposes, benefits and drawbacks, three budgeting methods, variance rules, flexing and a self-test.

Subject
Business
Level
AS LEVEL
Topic
Finance and accounting
Updated

Aligned to Cambridge A Level Business (9609), For examination in 2026, 2027 and 2028. Official specification .

Syllabus page (what it covers and how it is assessed): Cambridge A Level Business.

Syllabus points this page covers

9609 (AS Level)

  • 5.5 Budgets

Found an error? Report a correction.

Need help with this topic? Request a free trial class for A Level Business (9609).

Condensed notes for 5.5 Budgets (Cambridge International AS & A Level Business 9609, 2026–2028). Worked examples on building a budget, zero budgeting and flexing variances are in the Budgets study guide; exam-style questions are in the Budgets practice questions.

What 5.5 asks you to handle

  • 5.5.1 Measuring performance; benefits and drawbacks; incremental, flexible and zero budgeting; budgets for measuring performance, allocating resources, controlling and monitoring.
  • 5.5.2 Adverse and favourable variances; calculating and interpreting them.

Key terms

Term Meaning
Budget A financial plan for a future period, agreed in advance
Forecast A prediction of what is likely to happen
Budget holder Manager responsible for keeping to a budget
Incremental budget Last period’s budget adjusted by a percentage
Flexible budget Budget adjusted to the actual level of output
Zero budgeting Every item starts at zero and must be justified
Variance Difference between budgeted and actual figures
Favourable variance Raises profit: revenue above budget or costs below
Adverse variance Lowers profit: revenue below budget or costs above
Budget slack Padding a budget so targets are easy to meet

Building a budget

Sales budget → production/purchasing budget → cost budgets → department budgets → overall budget and planned profit. The sales forecast drives everything: if it is wrong, every budget is wrong.

Four uses

  1. Measuring performance: actual against plan.
  2. Allocating resources: who gets how much.
  3. Controlling: spending limits.
  4. Monitoring: progress checks during the period.

Benefits

Direction and coordination · early warning of overspending · motivation if managers take part · accountability through budget holders.

Drawbacks

Time and cost · inaccurate forecasts · rigidity (missed opportunities) · budget slack · “spend it or lose it” · demotivation if imposed and unrealistic.

Choosing a method

Method Best for Weakness
Incremental Stable activities Carries forward waste
Flexible Output that varies Needs fixed/variable split; more complex
Zero Cost reviews, new projects Slow; needs training

Variance rules

  • Revenue: actual above budget → F; below → A.
  • Costs: actual below budget → F; above → A.
  • Profit variance = sum of revenue and cost variances (F adds, A subtracts).
  • Always label F or A.

Worked reminder: a variance table

A shop budgets revenue $40 000, stock $22 000 and wages $9 000. Actual: revenue $38 500, stock $21 200, wages $9 400.

Item Variance
Revenue $1 500 A
Stock $800 F
Wages $400 A
Profit $1 100 A

Check: budgeted profit $9 000; actual profit $7 900; difference $1 100 A. The profit variance always equals the favourable variances minus the adverse ones.

Flexing in three steps

  1. Variable cost per unit = original budget ÷ budgeted output.
  2. Flexed budget = variable cost per unit × actual output (fixed costs unchanged).
  3. Variance = flexed budget − actual (label F or A).

Quick check: materials budget $24 000 for 8 000 units = $3 a unit. Actual output 9 000 units, actual materials $28 500. Flexed = $27 000. Variance = $1 500 A (not $4 500 A).

Interpreting variances

  • Favourable ≠ good: cheaper materials may lower quality.
  • Adverse ≠ bad: more sales need more materials.
  • Flex first when output differs from plan.
  • Size matters: compare with the budget (as a %); act on large or growing variances.
  • Controllable? Do not blame managers for external causes such as national energy prices.

Causes and actions

Variance Causes Actions
Revenue A Price cut, lower volume, rival Review price, promotion
Materials A Supplier price, waste, volume Negotiate, reduce waste
Labour A Overtime, pay rise, inefficiency Rotas, training
Overheads A Energy, repairs Investigate controllability

Exam traps

  • Higher cost than budget is adverse, never favourable.
  • Do not judge costs without flexing if output changed.
  • Budget ≠ forecast.
  • Incremental budgets can hide waste.
  • Zero budgeting is thorough but slow.
  • State whether you are comparing with the original or the flexed budget.

Self-test

  1. Distinguish between a budget and a forecast.
  2. Give two uses of budgets.
  3. Why is the sales budget usually prepared first?
  4. Give one drawback of incremental budgeting.
  5. When is zero budgeting most useful?
  6. Budgeted revenue is $60 000; actual revenue is $57 000. State the variance.
  7. Budgeted wages are $12 000; actual wages are $11 400. State the variance.
  8. Explain why a favourable materials variance may be bad news.
  9. Labour budget is $10 000 for 5 000 units. Actual output is 6 000 units and labour costs $12 600. Calculate the flexed budget and the variance.
  10. What is budget slack?
  11. Give one way to reduce “spend it or lose it” behaviour.
  12. Why should managers not be blamed for every adverse variance?

Answers

  1. A budget is an agreed plan with targets and limits for which someone is responsible; a forecast is a prediction of what is likely to happen.
  2. Any two: measuring performance, allocating resources, controlling, monitoring.
  3. Most other budgets depend on the expected level of sales.
  4. For example, it carries forward past inefficiencies.
  5. When spending needs a full review, such as in a cost-cutting drive or for a new project.
  6. $3 000 adverse.
  7. $600 favourable.
  8. It may come from cheaper, lower-quality materials, leading to complaints and lost sales.
  9. $2 per unit × 6 000 = $12 000 flexed; variance $600 adverse.
  10. Padding a budget, such as overstating costs or understating sales, so targets are easy to meet.
  11. For example, zero budgeting, or allowing unspent money to be carried forward.
  12. Some variances have external causes outside their control, such as a national rise in energy prices.