Skip to content
Marlbridge

Practice Questions

Cambridge A Level Information Technology (9626): Flowcharts – Practice Questions

Twelve original Cambridge 9626 IT section 4.2 questions with answers on flowchart symbols, tracing, drawing, editing and finding errors.

Subject
ICT
Level
AS LEVEL
Topic
Topic 4 – Algorithms and flowcharts
Updated

Aligned to Cambridge A Level Information Technology (9626), 2025-2027. Official specification .

Syllabus page (what it covers and how it is assessed): Cambridge A Level Information Technology.

Syllabus points this page covers

9626 (AS Level)

  • 4.2 Flowcharts

This page covers 1 of the 2 subtopics in topic 4, Algorithms and flowcharts.

Found an error? Report a correction.

Need help with this topic? Request a free trial class for A Level Information Technology (9626).

These are original questions written for Marlbridge, for revision and practice on this content. They are not reproduced past-paper questions, and they do not replicate the exam’s exact structure, question count or mark tariffs; examination boards hold copyright in their own papers. Use these alongside the official past papers available free from your board.

Related: Flowcharts study guide | Flowcharts revision notes

These questions are for section 4.2 Flowcharts (Topic 4, AS Level) of Cambridge International AS & A Level Information Technology (9626), 2025–2027. Flowcharts are shown as tables of numbered boxes. When you are asked to draw one, use the standard symbols. All organisations are invented.


Section A

1. Name the flowchart symbol used for each of these.

(a) Showing START. [1]

(b) Asking a question with two possible answers. [1]

(c) Showing total ← total + 1. [1]

2. State what is meant by a connector in a flowchart. [2]

3. State two rules about the flow lines leaving a decision symbol. [2]

4. Explain how a loop is shown on a flowchart. [2]

Section B

5. Flowchart A is shown below.

Box Symbol Contents Next
1 Terminator START 2
2 Process n ← 1 3
3 Process total ← 0 4
4 Decision n > 4? Yes: 7. No: 5
5 Process total ← total + n * n 6
6 Process n ← n + 1 4
7 Input/output OUTPUT total 8
8 Terminator STOP none

(a) Complete a trace table with columns for n and total and write down the output. [4]

(b) State the change needed to the flowchart so that it outputs the total of the squares of the numbers from 1 to 6. State the new output. [2]

6. A cinema charges nothing for children under 5, 6 pounds for people aged 5 to 64 and 4 pounds for people aged 65 or over. Draw a flowchart, or write it as a table of numbered boxes like Flowchart A, that inputs an age and outputs the price. [6]

7. Flowchart B is meant to input a number and output “Big” if it is over 10 and “Small” otherwise.

Box Symbol Contents Next
1 Input/output INPUT number 2
2 Decision number > 10? Yes: 3
3 Input/output OUTPUT “Big” 4
4 Input/output OUTPUT “Small” none

Identify three errors and say how each should be corrected. [6]

8. Flowchart C is meant to output the multiples of 4 that are less than 20.

Box Symbol Contents Next
1 Terminator START 2
2 Process m ← 4 3
3 Decision m < 20? Yes: 4. No: 5
4 Input/output OUTPUT m 3
5 Terminator STOP none

(a) Explain what will happen when Flowchart C is followed. [2]

(b) Describe the change that corrects it. [1]

(c) State the values output by the corrected flowchart. [2]

9. A flowchart contains a subroutine symbol labelled CheckPIN. Explain two reasons for using a subroutine symbol rather than drawing all the steps in the main flowchart. [4]

10. A flowchart for a lift controller has a decision weight > 600? with the Yes branch leading to OUTPUT "Overloaded" and the No branch leading to OUTPUT "Go". A tester wants to check the boundary.

(a) State the values of weight that should be tested. [2]

(b) Explain why the value 600 is an important test. [2]

11. Draw, or write as a table of numbered boxes, a flowchart that repeatedly inputs a number until the number entered is between 1 and 10 inclusive, then outputs “Accepted”. [5]

12. Write a pseudocode algorithm equivalent to Flowchart A in Question 5. [4]


Answers

1. (a) Terminator (rounded rectangle) [1].

(b) Decision (diamond) [1].

(c) Process box (rectangle) [1]. [3]

2. A small circle containing a letter or number [1] that joins one part of a flowchart to another with the matching connector, for example on another page [1]. [2]

3. Any two from: there must be exactly two flow lines leaving a decision [1]; each must be labelled (Yes/No or True/False) [1]; one line enters the decision [1]. [2]

4. A flow line is drawn back to an earlier box [1], and a decision controls whether the flow goes back or leaves the loop [1]. [2]

5. (a)

n total
1 0
2 1
3 5
4 14
5 30

Correct values of total after each pass, 1, 5, 14, 30 [3]. Output 30 [1].

(b) Change box 4 to n > 6? [1]. The new output is 91 (1 + 4 + 9 + 16 + 25 + 36) [1]. [6]

6. One possible answer: START [1]; INPUT age [1]; decision age < 5? with Yes to OUTPUT 0 and No to the next decision [1]; decision age < 65? with Yes to OUTPUT 6 and No to OUTPUT 4 [2]; all outputs lead to STOP, and decisions have both exits labelled [1]. [6]

7. Any three from: the flowchart has no START terminator [1], add one before box 1 [1]; the decision has no No exit [1], add a No branch to OUTPUT “Small” [1]; box 3 leads to box 4, so “Big” is followed by “Small” [1], box 3 should lead to STOP [1]; there is no STOP terminator at the end [1], add one after the outputs [1]. [6]

8. (a) m is never changed inside the loop [1], so m stays at 4 and the flowchart outputs 4 forever (an endless loop) [1].

(b) Add a process box m ← m + 4 between box 4 and box 3 [1].

(c) 4, 8, 12, 16 [2]. [5]

9. Any two from, each with a development: the steps are drawn once and the symbol can be reused wherever the task is needed [1], which saves space and avoids repeating work [1]; the main flowchart is shorter and easier to follow [1], because the detail is separated [1]; the subroutine can be drawn and tested separately [1], so errors are easier to find [1]. [4]

10. (a) 599, 600 and 601 (accept 600 and 601) [2].

(b) The condition is >, not >=, so 600 itself must give “Go” [1]. If the comparison was wrong, 600 would wrongly be output as overloaded, and boundary errors are the most common [1]. [4]

11. Sample answer: START [1]; INPUT number [1]; decision number > 0 AND number < 11? [1]; Yes leads to OUTPUT “Accepted” then STOP [1]; No leads back to the INPUT box (loop) [1]. [5]

12. Sample answer:

n ← 1
total ← 0
WHILE n < 5
    total ← total + n * n
    n ← n + 1
ENDWHILE
WRITE total

One mark each for: initialising n and total [1]; a loop that stops when n is greater than 4 (the condition n < 5 or equivalent) [1]; total increased by n squared inside the loop [1]; n increased inside the loop and total output after the loop [1]. [4]

Where marks are usually lost

  • Drawing a decision with one exit, or with exits not labelled.
  • Using the wrong symbol for a calculation or an input.
  • Leaving out START or STOP.
  • Making loops that do not change the tested value.
  • Testing only one normal value and missing the boundary.