Cambridge A Level Information Technology (ICT): 15.3 Tools and techniques for project management tasks (9626) – Practice Questions

Original practice questions with marked answers on Gantt charts, PERT networks, float and the critical path for section 15.3 of Cambridge A Level IT 9626.

Subject
ICT
Level
A LEVEL
Topic
Project management
Updated

Aligned to Cambridge A Level Information Technology (9626), 2025-2027. Official specification .

Syllabus page (what it covers and how it is assessed): Cambridge A Level Information Technology.

Syllabus points this page covers

9626 (A Level)

  • 15.3 Tools and techniques for project management tasks

This page covers 1 of the 3 subtopics in topic 15, Project management.

Found an error? Report a correction.

Need help with this topic? Request a free trial class for A Level Information Technology (9626).

These are original questions written for Marlbridge, for revision and practice on this content. They are not reproduced past-paper questions, and they do not replicate the exam’s exact structure, question count or mark tariffs – examination boards hold copyright in their own papers. Use these alongside the official past papers from your board or school.

These questions cover section 15.3 Tools and techniques for project management tasks of the Cambridge International AS & A Level Information Technology 9626 syllabus for examination in 2025, 2026 and 2027 (version 4). This is A Level only content examined in Paper 3 (Advanced Theory), where calculators are not allowed. Every question can be answered on paper. In the networks, time is measured in days from day 0.

Revise first with the study guide and revision notes. The Cambridge A Level IT hub lists every topic.

Questions

1. Define the term float in project management. [2]

2. Explain the difference between a task and a milestone on a project plan. [2]

3. A project plan shows these tasks. Task P runs from day 0 to day 4. Task Q runs from day 4 to day 9. Task R runs from day 4 to day 7. Task S runs from day 9 to day 11 and cannot start until both Q and R are finished.

(a) State which tasks are in progress on day 5. [1]
(b) State the planned finish day of the project. [1]
(c) Task R is delayed and now finishes on day 10. Explain the effect on the project. [2]

4. A company is building a stock-control system. The tasks, their durations in days and their dependencies are shown.

Task Duration Depends on
A Gather requirements 4 none
B Design database 3 A
C Design screens 6 A
D Build database 2 B
E Build screens 5 B, C
F Connect and test 3 D, E
G Write user guide 2 C
H Train staff 4 F, G

(a) State the earliest start day of task E and explain how you found it. [2]
(b) State the minimum time in which the project can be completed. [1]
(c) Calculate the float of tasks B, D and G. [3]
(d) List the tasks on the critical path. [2]
(e) Task C takes 3 days longer than planned. State the new project duration and explain your answer. [2]
(f) Task B takes 8 days instead of 3. Explain why the project is delayed by 2 days, and state what has happened to the critical path. [3]

5. The project manager of the stock-control system in Question 4 has two extra programmers available for one week. Using critical path analysis, explain which tasks they should be allocated to and why. [3]

6. Describe three ways in which critical path analysis can help a project manager to control a project. [3]

7. A small project has 12 tasks, several of which run at the same time. The manager is deciding between a Gantt chart and a PERT chart for the weekly progress meeting.

Evaluate the use of each, and recommend which should be used at the meeting. [6]

8. Give one disadvantage of using the critical path method on a long project. [1]

Answers

1. Float is the amount of time a task can be delayed [1] without delaying the completion of the whole project (LS - ES). [1] [2] Examiner insight: “Spare time” alone is a weak answer; say what the delay does not affect.

2. A task has a duration, it is work that takes time and resources [1]; a milestone has no duration and marks a key point such as “design approved” or “testing complete”. [1] [2]

3. (a) Q and R. [1] [1]
(b) Day 11. [1] [1]
(c) S cannot start until R is done, so S would start at day 10 instead of day 9 [1] and finish on day 12, so the project finishes one day late. [1] [2]
Examiner insight: R originally had 2 days of float (finish day 7, needed by day 9), so a delay to day 10 uses it all and goes 1 day further. Show the 2-day float or the start of S.

4. (a) 10 [1]. E needs both B (finishes day 7) and C (finishes day 10), so it starts at the later of the two. [1] [2]
(b) 22 days. [1] [1]
(c) B: float 3 [1]. D: float 6 [1]. G: float 6. [1] [3] Working: B ES 4, LS 7. D ES 7, LS 13. G ES 10, LS 16 (G needs to finish by day 18, when H starts).
(d) A, C, E, F, H (any four correct and in order for 1 mark; all five for 2). [2] [2] Check: 4 + 6 + 5 + 3 + 4 = 22.
(e) 25 days [1]. C is on the critical path with no float, so the 3 days are added directly to the project. [1] [2]
(f) B has 3 days of float, so it can overrun by 3 days without effect [1]. The overrun is 8 - 3 = 5 days, which is 2 days more than the float, so B now finishes on day 12, E starts on day 12 instead of day 10 and the project finishes on day 24 [1]. The critical path now runs through B (A, B, E, F, H) instead of through C. [1] [3]
Examiner insight: A delay costs project time only when it is larger than the float. Show the comparison of the overrun with the float.

5. Allocate them to critical tasks: A, C, E, F or H [1], because only speeding up critical tasks shortens the project [1]. They should not be allocated to B, D or G, which have float, so finishing them sooner would not bring the end date forward. [1] [3] Examiner insight: Reasons must refer to float or critical tasks; “they are the biggest tasks” does not score.

6. Any three from, one mark each for the use and a linked explanation:

  • Authorising work: release work on critical tasks first and watch their start dates, while work with float can be authorised later. [1]
  • Costings: pay for extra people or overtime only on critical tasks, as speeding up a task with float saves no time; costs can be linked to task dates to give a budget over time. [1]
  • Allocating resources: move staff and equipment from tasks with float to critical tasks. [1]
  • Monitoring: recalculate when a task is late, because the critical path may change. [1] [3]

7. Gantt chart: easy to read and understand [1]; shows what is running in parallel this week and how far each task has progressed [1]; poor at showing dependencies and float on 12 tasks. [1] PERT chart: shows dependencies and lets the critical path and float be calculated [1]; harder to read, takes longer to draw and redraw, and depends on accurate estimates. [1] Conclusion (one mark): a justified recommendation, for example use the Gantt chart for the weekly meeting to report progress and keep the PERT/CPM analysis for the manager to decide where delays matter. [1] [6] Examiner insight: “Evaluate” needs a judgement. Without a clear recommendation linked to the meeting, the answer is unlikely to reach full marks.

8. The critical path can change as tasks overrun or finish early, so the calculation must be repeated often. (Also accept: it depends on accurate duration estimates, which are hard to make on long projects.) [1] [1]

Where marks are usually lost

  • Adding all task durations rather than using the longest dependent path.
  • Taking the smaller finish time at a merge point on the forward pass.
  • Giving float as “extra time” without linking it to the project end date.
  • Describing a milestone as a short task.
  • Listing advantages and disadvantages without a conclusion in an “evaluate” question.
  • Recommending extra resources for tasks that have float.

More on this topic

Frequently asked questions

Is project management examined in Paper 3? Yes. Project management is topic 15 of Cambridge International AS & A Level Information Technology (9626) and is A Level only. It is examined in Paper 3 Advanced Theory.

Do I need a calculator for PERT and critical path questions? No. Calculators are not allowed in Paper 3, and the durations are small whole numbers, so the forward and backward passes can be done by hand.

Official syllabus

Cambridge International AS & A Level Information Technology 9626, syllabus for examination in 2025, 2026 and 2027, version 4, Cambridge University Press & Assessment. Section 15.3: Tools and techniques for project management tasks.