Practice Questions
Cambridge A Level Information Technology (9626): The stages of the project life cycle – Practice Questions
Thirteen original Cambridge 9626 IT section 15.1 questions with answers on project initiation, planning, execution, monitoring and close.
- Subject
- ICT
- Level
- A LEVEL
- Topic
- Topic 15 – Project management
- Author
- Marlbridge Academic Team
- Updated
- Reviewed by
- Harris Khan (what this means)
Aligned to Cambridge A Level Information Technology (9626), 2025-2027. Official specification .
Syllabus page (what it covers and how it is assessed): Cambridge A Level Information Technology.
Syllabus points this page covers
9626 (A Level)
- 15.1 The stages of the project life cycle
This page covers 1 of the 3 subtopics in topic 15, Project management.
Found an error? Report a correction.
Need help with this topic? Request a free trial class for A Level Information Technology (9626).
These are original questions written for Marlbridge, for revision and practice on this content. They are not reproduced past-paper questions, and they do not replicate the exam’s exact structure, question count or mark tariffs; examination boards hold copyright in their own papers. Use these alongside the official past papers available free from your board.
Related: The stages of the project life cycle study guide | Project management revision notes
These questions are for section 15.1 The stages of the project life cycle (Topic 15, A Level) of Cambridge International AS & A Level Information Technology (9626), 2025–2027. All organisations and figures are invented.
Section A
1. Name the four stages of the project life cycle in order. [2]
2. Define the term stakeholder and give one example. [2]
3. State what is meant by project scope. [2]
4. Explain what is meant by scope creep and why it is a problem. [2]
5. Give two reasons for holding a project review. [2]
6. Identify two things that are monitored during a project. [2]
Section B
7. Hartwell Council plans an online booking system for its leisure centres. The phases and durations are: requirements 4 weeks, build 6 weeks, testing 5 weeks, launch and training 3 weeks. The phases run one after another.
(a) Calculate the total duration of the project in weeks. [1]
(b) The council wants the system live in 15 weeks. Suggest two ways in which this could be achieved. [4]
8. The testing phase needs 4 testers working for 12 days each. A tester costs £200 per day.
(a) Calculate the effort in person-days and the cost. [2]
(b) Only 3 testers are available. Calculate how many days the testing will take, and state the effect on the cost. [3]
9. The online booking system has a budget of £90,000. At month 4, the plan said that 40% of the work would be complete. In fact, 30% is complete and £31,500 has been spent.
(a) Calculate the planned value of the work and the earned value of the work done. [2]
(b) Calculate the schedule variance and the cost variance, and state what each shows. [4]
(c) Suggest two actions the project manager could take. [2]
10. Write two SMART success criteria for the booking system. [4]
11. Describe the activities carried out in the project initiation stage. [6]
12. Explain why a project manager must report regularly to stakeholders, and describe what a good report contains. [5]
13. Evaluate the importance of the project close stage for the council. [6]
Answers
1. Initiation [1], planning, execution and monitoring, close [1 for all three in the correct order]. [2]
2. Anyone affected by or interested in the project [1]. Example: the sponsor, the end users, the project team, or a supplier [1]. [2]
3. What is included in the project [1] and what is not, so the boundaries of the work are clear [1]. [2]
4. Extra features or tasks are added without agreeing changes to time and budget [1]. The project becomes late and over budget, and quality may suffer [1]. [2]
5. Any two from: to check whether the objectives were met [1]; to learn lessons for future projects [1]; to identify good practice [1]; to check that stakeholders are satisfied [1]; to provide a record of what happened [1]. [2]
6. Any two from: progress against time [1]; cost [1]; quality [1]. [2]
7. (a) 4 + 6 + 5 + 3 = 18 weeks [1].
(b) Any two, each with a reason: overlap tasks, such as starting training during the last week of testing, so that the total is shorter [1][1]; add more staff to the build or test phases, to finish them sooner (though this raises the cost) [1][1]; reduce the scope, such as dropping some features, so there is less to build and test [1][1]; simplify the requirements phase [1][1].
8. (a) 4 × 12 = 48 person-days [1]; 48 × 200 = £9,600 [1].
(b) 48 ÷ 3 = 16 days [1]; the total person-days are the same so the cost stays at £9,600 [1], but the phase takes 4 days longer [1].
9. (a) Planned value = 0.40 × 90,000 = £36,000 [1]; earned value = 0.30 × 90,000 = £27,000 [1].
(b) Schedule variance = 27,000 − 36,000 = −£9,000 [1], so the project is behind schedule [1]. Cost variance = 27,000 − 31,500 = −£4,500 [1], so it is over budget [1].
(c) Any two from: add staff to the late tasks [1]; reduce the scope [1]; reorder or overlap tasks [1]; renegotiate the deadline or budget with the sponsor [1]; find and fix the cause of delays [1].
10. Any two criteria, each [1] for a measurable target and [1] for a time or a number: for example, residents can complete a booking in under 3 minutes [2]; the system is live in all five leisure centres by the end of week 18 [2]; at least 90% of bookings are made online within three months of launch [2]; the project is completed within the £90,000 budget [2]. [4]
11. Any six from: identifying the objectives [1]; deciding the resources needed [1]; setting the success criteria [1]; identifying the stakeholders and their needs [1]; defining the scope [1]; developing a high-level schedule [1]; deciding whether the project is feasible and affordable [1]; producing a project brief for approval [1]. [6]
12. Stakeholders need to know progress, costs, risks and problems [1], so that they can make decisions and give approval [1]. Early reports of problems allow action while it is still possible [1]. A good report is short and clear [1], and gives progress against time, cost and quality, and risks and decisions needed, in a form suited to the reader [1]. [5]
13. The council confirms that the deliverables meet the success criteria and signs them off [1]; the system is handed over with documentation and training, so staff can use it [1]; support arrangements are agreed [1]; suppliers are paid and resources released [1]. The review compares results with the plan [1], and the lessons learned help future projects so mistakes are not repeated [1]. Without close, faults and unmet needs may be left, and the lessons lost [1]. Judgement: it is important because it ensures benefits and learning, though it must be carried out properly and not skipped when the pressure is over [1]. Maximum 6 marks. [6]
Where marks are usually lost
- Listing stage names with no activities.
- Success criteria that cannot be measured.
- Giving the cost of a phase without the effort calculation in person-days.
- Saying variances are “bad” without stating whether the project is late or over budget.
- Ignoring the project review in the close stage.
Related resources
-
Study guides
Cambridge A Level Information Technology (9626): Project management software
Cambridge 9626 IT section 15.2 study guide: desktop, web-based and mobile project management software, uses in planning and scheduling, and trade-offs.
ICT · Cambridge · A Level
Read guide -
Practice questions
Cambridge A Level Information Technology (9626): Project management software – Practice Questions
Thirteen original Cambridge 9626 IT section 15.2 questions with answers on types and uses of project management software and their trade-offs.
ICT · Cambridge · A Level
Try questions -
Revision notes
Cambridge A Level Information Technology (9626): Project management software – Revision Notes
Revision notes for Cambridge 9626 IT section 15.2: types and uses of project management software, trade-offs and a twelve-question self-test.
ICT · Cambridge · A Level
Revise topic
Get free revision emails (optional)
Occasional emails with practice questions, worked explanations and links to free resources for the qualification and subjects you choose. No spam, and you can unsubscribe from any email. The free tools on this site never need an email.