Practice Questions
Cambridge A Level Information Technology (ICT): 16.1 The stages in the system life cycle (9626) – Practice Questions
Original practice questions with marked answers on systems and the stages of the system life cycle for section 16.1 of Cambridge A Level IT 9626.
- Subject
- ICT
- Level
- A LEVEL
- Topic
- System life cycle
- Author
- Marlbridge Academic Team
- Updated
- Reviewed by
- Harris Khan (what this means)
Aligned to Cambridge A Level Information Technology (9626), 2025-2027. Official specification .
Syllabus page (what it covers and how it is assessed): Cambridge A Level Information Technology.
Syllabus points this page covers
9626 (A Level)
- 16.1 The stages in the system life cycle
This page covers 1 of the 10 subtopics in topic 16, System life cycle.
Found an error? Report a correction.
Need help with this topic? Request a free trial class for A Level Information Technology (9626).
These are original questions written for Marlbridge, for revision and practice on this content. They are not reproduced past-paper questions, and they do not replicate the exam’s exact structure, question count or mark tariffs – examination boards hold copyright in their own papers. Use these alongside the official past papers from your board or school.
These questions cover section 16.1 The stages in the system life cycle of the Cambridge International AS & A Level Information Technology 9626 syllabus for examination in 2025, 2026 and 2027 (version 4). This is A Level only content examined in Paper 3 (Advanced Theory), where calculators are not allowed. All questions can be answered on paper.
Revise first with the study guide and the topic revision notes. The Cambridge A Level IT hub lists every topic.
Questions
1. Define the term system. [2]
2. State whether each of the following is a hardware system, a software system or a combination of hardware and software.
(a) A traffic-light controller made up of lamps, a timer unit, road sensors and the program that changes the lights. [1]
(b) A stock-control package running on a company’s existing computers. [1]
(c) A set of network cables, switches and routers joining the rooms of a school. [1]
3. The stages of developing a system are shown below in the wrong order:
implementation, analysis, evaluation, design, documentation, development and testing
Write the stages in the correct order. [3]
4. State the stage of the system life cycle in which each of the following takes place.
(a) The analyst interviews the managers of a clinic about their problems with the current appointment system. [1]
(b) The team draws a data flow diagram and designs the input forms. [1]
(c) The developers write the program and run tests on each module. [1]
(d) The clinic’s receptionists are given a booklet explaining how to book a patient. [1]
5. Explain why the output of one stage is important to the stage that follows it. Use two different pairs of stages in your answer. [4]
6. A clinic’s new appointment system has been written. During testing, the testers find that there is no field on the input form for a patient’s mobile number, which the user requirements specification says is needed.
(a) Name the stage the team should return to, and justify your choice. [2]
(b) Describe what must be done before the system is tested again. [2]
7. Six months after a retail company introduced a new online ordering system, an evaluation shows that customers want to pay by a new method that did not exist when the system was designed.
Explain how this shows that the stages form a cycle and not a straight line. [3]
8. A manager says: “Documentation can wait until the system has been running for a year.” Discuss this view. [4]
Answers
1. A collection of components [1] that work together to form a whole. [1] [2] Examiner insight: “A computer” or “a program” is not a definition; the answer needs the idea of components forming a whole.
2. (a) A combination of hardware and software. [1] [1]
(b) A software system. [1] [1]
(c) A hardware system. [1] [1]
Examiner insight: The words “existing computers” in (b) matter: the system being developed is the software.
3. Analysis, design, development and testing, implementation, documentation, evaluation. Award 3 marks for all six in the correct order, 2 marks for one adjacent pair swapped, 1 mark for analysis first and evaluation last with the middle incorrect. Accept documentation before implementation. [3] Examiner insight: In real projects documentation is written throughout, so either order of implementation and documentation is accepted; do not move analysis, design or evaluation.
4. (a) Analysis. [1] [1]
(b) Design. [1] [1]
(c) Development and testing. [1] [1]
(d) Documentation (user documentation). [1] [1]
5. Two pairs, each with a stage output and its use (2 marks each):
- The specifications from analysis [1] tell the designers what the system must do, so the design can be checked against them. [1]
- The design from the design stage [1] tells developers what to build, so they build forms and files to a plan. [1]
- The tested system [1] is what is implemented, so users receive a system that has been checked. [1]
- The specifications from analysis [1] are what evaluation compares the live system with. [1] Accept any two valid pairs. [4] Examiner insight: Name the output, such as the specification or design, then say what the next stage does with it.
6. (a) Design [1], because the mobile number field is missing from the form design, so the fault is in the design and not just in the code. (Accept analysis or design with a valid justification; do not accept implementation.) [1] [2]
(b) Add the field to the design of the input form and the data storage, and update the design documents [1]; then change the program and database to match and retest the new field and the parts that use it. [1] [2]
7. Evaluation found a new need [1]. This is fed back to analysis, where a new user requirement is written [1], and the later stages (design, development and testing, implementation) are repeated for the change, so the process goes round again. [1] [3]
8. For (up to 1 mark): there is no urgency if the system is not yet changing, and writing it later may save effort. Against (up to 3 marks):
- Documentation is needed from analysis and design onward to record the requirements and design, which developers and testers use. [1]
- Users need user documentation when the system is implemented, or they cannot use it properly, and the help desk will be overloaded. [1]
- Technical documentation is needed for maintenance; details are forgotten, or staff leave, if it waits a year. [1]
- Conclusion: the view is not sound; documentation should be produced during the project. [1] Maximum 4. [4] Examiner insight: “Discuss” needs both sides and a conclusion. A one-sided answer is capped.
Where marks are usually lost
- Defining a system as a computer or as a program.
- Writing analysis and design as if they mean the same thing: analysis finds what is needed, design plans how.
- Naming a stage without justifying it.
- Saying only “so it can be checked” without naming what is checked.
- Forgetting that evaluation can lead back to analysis.
- Recap with the topic revision notes.
- Reread the study guide.
- Explore the Cambridge A Level IT hub and the printable 9626 checklist.
- Try all free 10-minute diagnostics.
- Book a free trial class.
Frequently asked questions
Is the system life cycle on the Paper 3 syllabus? Yes. The system life cycle is topic 16 of Cambridge International AS & A Level Information Technology (9626) and is A Level only. It is examined in Paper 3 Advanced Theory.
Which stage comes first in the system life cycle? Analysis comes first. Without it, designers and developers do not know what the users need.
Official syllabus
Cambridge International AS & A Level Information Technology 9626, syllabus for examination in 2025, 2026 and 2027, version 4, Cambridge University Press & Assessment. Section 16.1: The stages in the system life cycle.
Related resources
-
Study guides
Cambridge A Level Information Technology (ICT): System life cycle (9626)
Study guide to the system life cycle for Cambridge A Level IT 9626: analysis, DFDs, testing, changeover, documentation, prototyping and maintenance.
ICT · Cambridge · A Level
Read guide -
Practice questions
Cambridge A Level Information Technology (ICT): System life cycle (9626) – Practice Questions
Original practice questions with marked answers on the system life cycle for Cambridge A Level IT 9626: DFDs, test plans, changeover and maintenance.
ICT · Cambridge · A Level
Try questions -
Revision notes
Cambridge A Level Information Technology (ICT): System life cycle (9626) – Revision Notes
Condensed revision notes on the system life cycle for Cambridge A Level IT 9626, with comparison tables, a quick self-test and common mark losses.
ICT · Cambridge · A Level
Revise topic
Get free revision emails (optional)
Occasional emails with practice questions, worked explanations and links to free resources for the qualification and subjects you choose. No spam, and you can unsubscribe from any email. The free tools on this site never need an email.