OCR A Level Business (H431): Conflicts in business decision making
Study guide to conflicts in decision making for OCR A Level Business H431: one proposal tested by five tools, resolving conflicts and why businesses fail.
- Subject
- Business
- Level
- A LEVELS
- Topic
- Business objectives and strategic decisions
- Author
- Marlbridge Academic Team
- Updated
- Reviewed by
- Salman Ahmad (what this means)
Aligned to OCR A Level Business (H431), Version 2.1 (January 2026), for first assessment in 2017; final assessment summer 2027. Official specification .
Syllabus page (what it covers and how it is assessed): OCR A Level Business.
Syllabus points this page covers
H431
- 1.16 Conflicts in business decision making
Found an error? Report a correction.
Need help with this topic? Request a free trial class for A Level Business (H431).
This guide covers the Conflicts in business decision making content in the area of study Business objectives and strategy of the OCR A Level Business (H431) specification, Version 2.1 (January 2026), final assessment summer 2027. It is numbered 1.16 on this site. The Ansoff’s matrix and conflicts in business decision making study guide explains why tools disagree and compares two projects with payback, ARR and NPV. This page goes further: it tests a single proposal with five different tools, including a decision tree and Ansoff’s matrix, shows a method for resolving the conflict, and works through an explanation of why a business failed. All businesses and figures are invented.
Use it with the conflicts in decision making revision notes and the conflicts in decision making practice questions. The course hub is OCR A Level Business.
What the specification asks for
| Learners should be able to | Covered below |
|---|---|
| explain why the results of one decision making tool may conflict with another | Why tools disagree |
| evaluate a business’s decisions based on quantitative and qualitative information | Worked example 1 |
| evaluate the likely success of a business proposal using decision making tools | Judging likely success |
| evaluate which course of action a business should take | Resolving the conflict |
| evaluate the usefulness, and the strengths and limitations, of decision making tools | Usefulness of the tools |
| evaluate reasons for success or failure of a business | Worked example 2 |
This content draws on tools from across the course, so it is often where a case study question brings everything together.
Why tools disagree
Each tool answers a different question, so it is no surprise that they can point in different directions.
| Tool | Question it answers | What it leaves out |
|---|---|---|
| Decision tree | Which option has the best average outcome, given the risks? | Timing of cash; qualitative factors |
| Payback | How quickly is the outlay recovered? | Cash after payback; time value of money |
| Average rate of return (ARR) | What is the average yearly return on the outlay? | Timing of cash |
| Net present value (NPV) | What are the cash flows worth in today’s money, less the cost? | Depends on the discount rate chosen |
| Ansoff’s matrix | How far does the option move from what the business knows? | Any figures at all |
| SWOT and qualitative views | Does it fit the business’s strengths, culture and mission? | Measurement |
A conflict usually means the tools are measuring different things, not that one of them is wrong.
Worked example 1: one proposal, five tools
Case. Kestle Leisure runs four gyms for adults. It is considering a £500,000 trampoline park for families. The finance director has prepared the following.
Decision tree. The park succeeds with probability 0.6, bringing total net cash inflows of £1.1 million over five years, or struggles with probability 0.4, bringing £300,000.
EV = (0.6 × 1,100,000) + (0.4 × 300,000) = 660,000 + 120,000 = £780,000. Net gain = 780,000 − 500,000 = £280,000.
Investment appraisal, using the expected annual inflows (£000), which total £780,000:
| Year | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| Net cash inflow | 100 | 140 | 160 | 180 | 200 |
- Payback: cumulative inflows are 100, 240, 400 and 580. After 3 years, £100,000 remains, which is 100 ÷ 180 = 0.56 of year 4, so payback is 3.56 years. Kestle’s target is 3 years.
- ARR: total profit = 780 − 500 = £280,000; average a year = £56,000; ARR = 56,000 ÷ 500,000 × 100 = 11.2%. Kestle’s target is 15%.
- NPV at 10%: using factors 0.909, 0.826, 0.751, 0.683 and 0.621, present values are 90.9 + 115.64 + 120.16 + 122.94 + 124.2 = £573,840, so NPV = +£73,840.
- NPV at 15%: using factors 0.870, 0.756, 0.658, 0.572 and 0.497, present values total £500,480, so NPV = +£480, almost zero.
Ansoff’s matrix. Family entertainment is a new product for a new customer group, so this is diversification. It is related, since Kestle knows how to run leisure sites, but it has no experience of children’s activities or safety.
Qualitative evidence. Managers say the gyms are quiet in the day and at weekends when families are free; there is no trampoline park within 20 miles; insurance for children’s activities is expensive.
Summary of the results
| Tool | Result | Points towards |
|---|---|---|
| Decision tree | Net gain £280,000 | Yes |
| Payback | 3.56 years, target 3 | No |
| ARR | 11.2%, target 15% | No |
| NPV at 10% | +£73,840 | Yes |
| NPV at 15% | +£480 | Marginal |
| Ansoff | Related diversification | Caution |
| Qualitative | Gap in local market; costly insurance | Mixed |
Explaining the conflict
- The decision tree says yes by a large margin because it adds up cash without discounting it: £1 in year 5 counts the same as £1 today.
- NPV discounts later cash, so the gain shrinks to £73,840 at 10% and almost vanishes at 15%. The project’s value is sensitive to the cost of finance.
- Payback says no because much of the cash comes late, in years 4 and 5.
- ARR says no because, averaged over five years, the return is below the target.
- Ansoff warns that the risk is higher than for Kestle’s usual decisions, which may mean the 0.6 probability is optimistic.
Resolving the conflict
A method for “evaluate which course of action”:
- Decide which tools matter most for this business’s objectives. If Kestle is short of cash, payback matters most; if it wants long-term value, NPV matters most.
- Find the weakest assumption. Here it is the 0.6 probability of success and the inflows in years 4 and 5, since the case depends on them.
- Test it. If success were only 0.5 likely, the tree’s EV would be £700,000 and net gain £200,000, still positive; but if every year’s inflow fell in the same proportion, NPV at 10% would drop to about £15,000 (573,840 × 700 ÷ 780 = £514,985, less £500,000).
- Bring in qualitative factors and stakeholders. Using quiet gym space suggests possible cost savings; children’s safety adds a risk to reputation.
- Make a judgement with a condition. For example: Kestle should go ahead only if it can finance the park at close to 10%, and should consider leasing equipment to cut the outlay, which would shorten payback. If finance costs 15%, the project adds almost no value and should be rejected.
Judging likely success
To evaluate the likely success of a proposal, ask:
- Are the inputs realistic? Compare forecasts with the business’s past record and with similar ventures.
- How sensitive is the result? Which single input, if wrong, would reverse the decision?
- Does the business have the resources? Cash, skills, management time.
- Does it fit the objectives and mission? A profitable project that contradicts the mission may damage the brand.
- How will competitors and stakeholders react?
Usefulness of the tools
Strengths of using several tools: each covers another’s blind spot; agreement between them gives confidence; disagreement shows exactly where the uncertainty lies. Limitations: all quantitative tools share the same forecasts, so if the forecasts are wrong, agreement is false comfort; tools take time and skill; managers may choose the tool that supports the answer they want. Tools are most useful when the forecasts are grounded in evidence and the decision is large enough to justify the analysis.
Worked example 2: reasons for success or failure
Case. Thrushcross Cafés grew from two cafés to nine in three years, funded by loans. It went into administration last year. The evidence:
- Sales per café were forecast at £6,000 a week; the new cafés averaged £3,900.
- Interest rates rose during the period, raising loan repayments.
- Three of the new sites were in towns where a national coffee chain had just opened.
- Staff turnover at new sites was over 60%; customer reviews mentioned slow service.
- The owners did not review the plan until the seventh café had opened.
Analysing the reasons. Separate internal from external causes and link them:
- External: rising interest rates and strong competition reduced demand and raised costs.
- Internal: over-optimistic forecasts (actual sales 35% below forecast); rapid expansion funded by debt; poor staff retention leading to poor service; no review stage, so the problem was not caught.
Judging the most important reason. The rise in interest rates and the arrival of competitors made success harder, but the business could have survived them if it had grown more slowly. The most important reason was the decision to expand rapidly on borrowed money using forecasts that were never tested: when sales fell 35% short, there was no cushion. A Plan-Do-Review cycle after the third café would have shown the gap before the debt became unmanageable.
The same structure, identify causes, sort internal from external, link them, then choose the most important with a reason, works for explaining success too.
Common mistakes
- Reporting each tool’s result without explaining why they differ.
- Assuming the most sophisticated tool, usually NPV, must be right.
- Ignoring the business’s objectives when deciding which tool matters most.
- Listing reasons for failure without saying which mattered most.
Exam technique
“Explain why tools conflict”: name what each measures and what it ignores. “Evaluate which course of action”: state the results, explain the conflict, test the weakest input, bring in qualitative factors and judge with a condition. “Evaluate reasons for success or failure”: prioritise.
Practise with the conflicts in decision making practice questions. Related content: decision trees and Ansoff’s matrix.
Official syllabus
OCR, Advanced GCE in Business (H431), specification Version 2.1 (January 2026), for first assessment in 2017: area of study Business objectives and strategy, content Conflicts in business decision making.
Related resources
-
Practice questions
OCR A Level Business (H431): Conflicts in business decision making – Practice Questions
Original OCR A Level Business H431 questions with full answers on conflicting decision tools, judging a proposal and explaining why a business failed.
Business · OCR · A Level
Try questions -
Revision notes
OCR A Level Business (H431): Conflicts in business decision making – Revision Notes
Revision notes on conflicts in decision making for OCR A Level Business H431: what each tool ignores, resolving conflicts, success and failure, and a self-test.
Business · OCR · A Level
Revise topic -
Study guides
OCR A Level Business (H431): Corporate social responsibility (CSR)
Study guide to CSR for OCR A Level Business H431: policy versus profile, the conflict with profit, when CSR matters most and how to improve a CSR profile.
Business · OCR · A Level
Read guide
Get free revision emails (optional)
Occasional emails with practice questions, worked explanations and links to free resources for the qualification and subjects you choose. No spam, and you can unsubscribe from any email. The free tools on this site never need an email.