Revision notes on stock control for OCR A Level Business H431: chart formulae, EOQ, JIT, kanban, methods compared, production methods and a self-test.

Subject
Business
Level
A LEVELS
Topic
Operational strategy
Updated

Aligned to OCR A Level Business (H431), Version 2.1 (January 2026), for first assessment in 2017; final assessment summer 2027. Official specification .

Syllabus page (what it covers and how it is assessed): OCR A Level Business.

Syllabus points this page covers

H431

  • 4.10 Stock control

Found an error? Report a correction.

Need help with this topic? Request a free trial class for A Level Business (H431).

Condensed notes on the Stock control content (4.10 on this site) in the area of study Productive efficiency, OCR A Level Business H431, Version 2.1 (January 2026), final assessment summer 2027. Full explanations and three worked examples are in the stock control study guide. Test yourself with the stock control practice questions. All figures are invented.

What the specification lists

  • Meaning of stock control.
  • Methods: stock control charts, just in time (JIT), kanban, fixed reorder stock level, fixed time reordering, economic order quantity (EOQ) and electronic methods.
  • Construct, calculate and interpret stock control charts: buffer stock, reorder level and quantities, lead time.
  • Evaluate the impact and importance of holding and controlling stock.
  • Evaluate the relationship between stock control and methods of production.

Core recall

Why stock matters

Holding stock Benefit Cost
Too much Meets demand peaks, bulk discounts Storage, insurance, cash tied up, waste, damage, out-of-date goods
Too little Low holding cost Stock-outs, idle workers, lost sales, rush orders

Chart terms and formulae

  • Buffer stock: minimum level, protection against delay or demand surges.
  • Lead time: order to delivery.
  • Reorder level = buffer stock + (daily usage × lead time).
  • Reorder quantity: amount ordered each time.
  • Maximum stock = reorder level + reorder quantity − (daily usage × lead time) = buffer + reorder quantity.
  • Time between orders = reorder quantity ÷ daily usage.
  • The specification gives no formulae; these are the standard forms.

Drawing the chart

  1. Time on the horizontal axis, stock on the vertical axis.
  2. Sloping line down at the usage rate.
  3. Horizontal lines at buffer and reorder level.
  4. Order placed at the reorder level; delivery after the lead time, when stock is at the buffer.
  5. Vertical line up to the maximum on delivery.

Methods compared

Method How it works Strength Weakness
Fixed reorder stock level Order a set quantity at the reorder level Responds to actual usage Needs constant monitoring
Fixed time reordering Order at set intervals; quantity varies Simple routine Needs bigger buffer; may over- or under-order
EOQ Order size with lowest ordering plus holding cost Cuts total cost Assumes steady demand and costs
JIT Stock arrives when needed Frees cash and space; less waste One late delivery halts production
Kanban Card or container signals a need for more Pulls stock by demand Needs discipline and reliable suppliers
Electronic Real-time records, automatic orders Accuracy and speed Cost; system failure

EOQ

EOQ = √(2 × annual demand × cost per order ÷ annual holding cost per unit).

  • At the EOQ, annual ordering cost equals annual holding cost.
  • Average stock is taken as half the order size.
  • Limits: ignores discounts, shelf life and changes in demand.

Stock control and production methods

Method of production Stock control point
Job Order for each job; long lead times for special items
Batch Stock builds between stages; reorder levels and EOQ suit shared materials
Flow Continuous supply essential; JIT or large buffer; kanban common

Evaluation points

  • Cost of holding against cost of shortages.
  • Cash flow and customer service.
  • Reliability of suppliers and lead time.
  • Perishable or fashion goods lose value quickly.
  • Stakeholders: employees (idle time), suppliers (tight timetable), customers (availability), owners (cash freed or sales lost).

Worked reminder

Hendry Paints (invented): usage 40 tins a day, lead time 5 days, buffer 150, reorder quantity 500.

  • Reorder level = 150 + 40 × 5 = 350.
  • Maximum stock = 350 + 500 − 200 = 650.
  • Time between orders = 500 ÷ 40 = 12.5 days.
  • Annual demand 10,000, order cost £80, holding cost £2.50: EOQ = √(2 × 10,000 × 80 ÷ 2.5) = √640,000 = 800.
  • Total cost at 500: £1,600 + £625 = £2,225. At 800: £1,000 + £1,000 = £2,000.
  • If lead time rises to 8 days, usage in the wait is 320 and the reorder level should be 470.

Key terms

Term Meaning
Stock (inventory) Materials, work in progress and finished goods held
Buffer stock Minimum stock level held as protection
Lead time Time from placing an order to receiving it
Reorder level Stock level at which a new order is placed
Stock-out Running out of stock
JIT Receiving stock only when needed
Kanban Card-based signal to replace used stock
EOQ Order size that minimises ordering plus holding cost

Exam traps

  • Multiply daily usage by lead time before adding the buffer.
  • Subtract usage in the lead time when finding the maximum.
  • Do not call JIT “always cheaper”; weigh supplier reliability.
  • Buffer stock is a minimum; reorder quantity is the amount ordered.
  • Show working for EOQ, and state its assumptions when evaluating.
  • Link the method to the production type and product in the case.

Self-test

  1. Define lead time.
  2. Usage is 30 units a day, lead time 4 days, buffer 80. Calculate the reorder level.
  3. The reorder quantity is 300. Calculate the maximum stock level.
  4. How many days pass between orders?
  5. Give two costs of holding too much stock.
  6. Give two effects of a stock-out.
  7. Annual demand is 3,600, order cost is £50, holding cost is £4 a unit. Calculate EOQ.
  8. What does kanban mean in stock control?
  9. Why is JIT risky for flow production?
  10. Give one benefit of electronic stock control.

Answers

  1. The time between placing an order and receiving it.
  2. 80 + (30 × 4) = 80 + 120 = 200 units.
  3. 200 + 300 − 120 = 380 units (also 80 + 300).
  4. 300 ÷ 30 = 10 days.
  5. Any two: storage cost; insurance; money tied up; waste or damage; products going out of date.
  6. Any two: lost sales; idle workers and machines; rush orders at high cost; customers lost to rivals.
  7. √(2 × 3,600 × 50 ÷ 4) = √90,000 = 300 units.
  8. A card or container signals that material has been used and more should be supplied, so production is pulled by demand.
  9. Continuous production stops at once if a delivery is late, and a stoppage is very costly.
  10. Any one: real-time stock records; automatic reordering; fewer errors.

Official syllabus

OCR, Advanced GCE in Business (H431), specification Version 2.1 (January 2026): area of study Productive efficiency, content Stock control.

Related resources

Get free revision emails (optional)

Occasional emails with practice questions, worked explanations and links to free resources for the qualification and subjects you choose. No spam, and you can unsubscribe from any email. The free tools on this site never need an email.