OCR AS Level Economics (H060): Costs and revenue – Practice Questions

Original OCR AS Level Economics (H060) practice questions on costs, revenue, profit and PED with total revenue, with full mark-scheme-style answers.

Subject
Economics
Level
AS LEVEL
Topic
Costs and revenue
Updated

Aligned to OCR AS Level Economics (H060), Version 3.0 (June 2026), for first assessment in 2020. Official specification .

Syllabus page (what it covers and how it is assessed): OCR AS Level Economics.

Syllabus points this page covers

H060

  • 2.6 Elasticity

Found an error? Report a correction.

Want a teacher for this? Marlbridge teaches Economics online. Request a free trial class.

Archived page. OCR’s current AS Level Economics (H060) specification, Version 3.0 (June 2026), does not include costs and revenue at AS Level; the topic is A Level (H460) content. This page is kept so existing links still work, but it is no longer part of the AS course. For the A Level topic, use the OCR A Level costs practice questions.

These are original questions written for Marlbridge, for revision and practice on this content. They are not reproduced past-paper questions, and they do not replicate the exam’s exact structure, question count or mark tariffs – examination boards hold copyright in their own papers. Use these alongside the official past papers from your board or school.

These questions cover Costs and revenue for the OCR AS Level Economics (H060) specification, for first assessment in 2016, Component 01, Microeconomics. The current specification names PED and a firm’s total revenue at AS, with fuller cost and revenue calculation at A Level, so check the scope with your teacher. The mark totals are our own and every firm and figure is invented. Explanations are in the costs and revenue study guide and the costs and revenue revision notes.

Questions 7 and 11 use this invented data for Firm Kestrel.

Output (units) 10 20 30 40 50
Price (£) 50 45 40 35 30
Total cost (£) 520 700 900 1,180 1,500

Questions

Section A: short questions

1. Distinguish between fixed costs and variable costs, giving an example of each. [2]

2. Which statement about the long run is correct?

A: All costs are fixed

B: All costs are variable

C: Fixed costs are greater than variable costs

D: Average cost is constant [1]

3. A café has fixed costs of £900 a week and variable costs of £1.50 per meal.

(a) Calculate total cost at 600 meals a week. [1]

(b) Calculate average cost at 600 meals. [1]

(c) Calculate average cost at 900 meals. [1]

4. A firm sells 2,500 units at £6.00. It raises the price to £6.60 and sales fall to 2,400.

(a) Calculate total revenue before and after the price rise. [2]

(b) Calculate the price elasticity of demand. [2]

5. Define average revenue and explain why it equals price when all units are sold at the same price. [2]

6. Total revenue rises from £3,600 to £3,900 when sales rise from 300 to 350 units. Calculate marginal revenue per unit. [1]

Section B: structured and extended questions

7. Use the data for Firm Kestrel.

(a) Calculate total revenue and profit at each output. [3]

(b) Identify the profit-maximising output and the revenue-maximising output in the table. [2]

(c) Identify the output with the lowest average cost. [1]

8. Explain why a cinema’s average cost per customer falls as more customers attend. [3]

9. Explain, with the aid of a diagram, how total revenue changes as price falls along a straight-line demand curve. [6]

10. A theatre’s costs for a performance are almost entirely fixed. Explain why it might sell unsold seats at a large discount shortly before the show. [4]

11. Firm Kestrel’s managers receive a bonus based on sales revenue. Using the data, explain how this could affect the firm’s output and profit. [4]

12. Evaluate whether a firm should cut its price in order to increase sales. [8]

Answers

1. Fixed costs do not change with output in the short run, such as rent [1]. Variable costs change with output, such as raw materials [1]. [2]

2. B [1]. In the long run all factors of production can be changed. [1]

3. (a) 900 + 1.50 × 600 = £1,800 [1].

(b) 1,800 ÷ 600 = £3.00 [1].

(c) (900 + 1,350) ÷ 900 = £2.50 [1]. [3]
Examiner insight: AC falls because the fixed £900 is spread over more meals; say so if asked to explain.

4. (a) Before: 6.00 × 2,500 = £15,000; after: 6.60 × 2,400 = £15,840 [1]. TR rises by £840 [1].

(b) % change in price = +10%, % change in quantity = −100 ÷ 2,500 = −4% [1]. PED = −4 ÷ 10 = −0.4 [1]. [4]

5. Average revenue is total revenue divided by the number of units sold [1]. If every unit sells at the same price, TR = P × Q, so TR ÷ Q = P [1]. [2]

6. MR = 300 ÷ 50 = £6 per unit [1]. [1]

7. (a) TR = £500, £900, £1,200, £1,400 and £1,500 [1]. Profit = −£20, £200 and £300 at 10, 20 and 30 units [1]; £220 and £0 at 40 and 50 units [1].

(b) Profit is maximised at 30 units (£300) [1]; revenue is maximised at 50 units (£1,500) [1].

(c) AC is £52, £35, £30, £29.50 and £30, so the lowest is at 40 units [1]. [6]
Examiner insight: The profit-maximising output need not be the lowest-cost output, because profit depends on revenue as well as cost.

8. Most of a cinema’s costs, such as rent, equipment and staff for each showing, are fixed [1]. As attendance rises, these fixed costs are spread over more customers, so average fixed cost falls [1]. The variable cost of an extra customer is very small, so average cost per customer falls [1]. [3]

9. Diagram of a straight-line demand curve with price and quantity axes, with revenue rectangles at a high and a low price [1]. Above the midpoint demand is price elastic [1], so a price cut raises quantity proportionately more and TR rises [1]. At the midpoint PED is −1 and TR is at its maximum [1]. Below the midpoint demand is inelastic [1], so further price cuts reduce TR [1]. [6]

10. Fixed costs must be paid whether or not the seats are sold [1], and an extra customer adds almost nothing to cost [1]. Any revenue from a discounted seat therefore adds to profit, or reduces the loss [1]. Last-minute buyers are likely to be price sensitive (elastic demand), so a discount can fill many seats [1]. [4]

11. Managers would push output towards 50 units, where TR is highest at £1,500 [1], instead of 30 units where profit is highest [1]. At 50 units profit is zero, compared with £300 at 30 units [1], so shareholders lose £300 of profit while managers gain a larger bonus [1]. [4] Examiner insight: Quote both outputs and both profit figures; the contrast is the point of the question.

12. Award up to 8 marks across knowledge, application, analysis and evaluation.

  • If demand is price elastic, a price cut raises TR [1], because quantity rises proportionately more than price falls [1].
  • Higher sales may also spread fixed costs, lowering average cost [1].
  • But extra sales add variable costs, so profit may fall even if revenue rises [1].
  • If demand is inelastic, the cut reduces TR and profit [1].
  • Rivals may match the cut, so the expected rise in sales does not happen [1].
  • A cut may suit other objectives, such as market share or growth [1].
  • Judgement: the firm should cut price only if demand is elastic, rivals are unlikely to follow, and the extra revenue exceeds the extra cost [1]. [8]

Where marks are usually lost

  • Calling a cost fixed because it is large.
  • Treating revenue and profit as the same thing.
  • Multiplying instead of dividing when finding average cost.
  • Leaving out units or “per unit”.
  • Giving one-sided answers to evaluation questions without a judgement.

Frequently asked questions

Why is profit not maximised where revenue is maximised? Near the revenue maximum, extra units add little to revenue but still add to cost, so profit starts to fall before revenue peaks.

Do fixed costs affect the best price to charge? Fixed costs must be paid whatever price is chosen, so the profit-maximising price depends on how revenue and variable costs change with output.

More on this topic