Topic 3.1.4: Financial management
- Financial objectives named in 7137
- Profit, profitability, cash flow, liquidity and levels of borrowing. Influences include owners and their attitude to risk, available cash, interest rates, competitors and the economy.
- Cash flow vs profit
- Profit is revenue minus costs over a period, counted when earned, even on credit. Cash flow records only money actually moving. Cash can arrive from a loan with no profit; profit can be earned long before cash arrives.
- Return on investment and gearing
- ROI = profit from the investment ÷ cost of the investment × 100 (£8,400 ÷ £60,000 = 14%). Gearing = non-current liabilities ÷ (total equity + non-current liabilities) × 100 (£80,000 ÷ £320,000 = 25%).
- Gross profit, operating profit and profit for the year
- Gross profit = revenue − cost of sales. Operating profit = gross profit − operating expenses. Profit for the year = operating profit + profit from other activities − net finance costs − tax.
- Revenue £90,000; cost of sales £54,000; operating expenses £25,200. Margins?
- Gross profit £36,000: gross margin 40%. Operating profit £10,800: operating margin 12%.
- Reading profit margins: what does a fall in each margin point to?
- A fall in gross margin points to higher cost of sales or lower prices. A fall in operating margin with a steady gross margin points to rising operating expenses. A widening gap down to profit for the year points to finance costs and tax.
- Budget variance: formula and how to label it
- Budget variance = budgeted figure − actual figure, labelled by its effect on profit: higher revenue or lower cost is favourable; lower revenue or higher cost is adverse. Example: materials budget £18,000, actual £16,200 → £1,800 favourable.
- Value and limits of budgeting
- Value: sets targets, controls spending, gives responsibility, coordinates departments, flags problems early. Limits: forecasts may be wrong; rigid budgets discourage flexibility; variances show what changed, not why.
- Cash-flow forecast: method
- Cash in − cash out = net cash flow. Closing balance = opening balance + net cash flow, carried forward as next month's opening balance. Credit sales count only when paid.
- Price £40, variable cost £24, fixed costs £56,000, planned 4,200 units. Break-even and profit?
- Contribution £16. Break-even = 56,000 ÷ 16 = 3,500 units. Margin of safety 700 units (16.7%). Profit = 16 × 4,200 − 56,000 = £11,200.
- Effect on break-even output of a price rise, a variable cost rise and a fixed cost rise
- Price rises: break-even falls (revenue line steeper). Variable cost rises: break-even rises (total cost line steeper). Fixed costs rise: break-even rises (total cost line starts higher).
- Internal and external sources of finance in 7137
- Internal: owners' investment, retained profits, sale of assets, sale and leaseback, working capital. External: trade credit, share capital, overdraft, loans, business angels, private equity, crowd funding.
- Ways of improving cash flow named in 7137
- Debt factoring, shortening payment time from customers, early payment incentives, credit checks, increasing payment time to suppliers, reducing outgoings, better invoice management. Risks: fees, lost income or customers, strained supplier relations.