- Operations objectives named in 7137
- Efficiency, quality, volume of goods and services, flexibility, and environmental impact.
- Added value
- Selling price less the cost of bought-in inputs. Example: price £85, bought-in materials £52 → £33, which is 38.8% of the price.
- Employee productivity, unit costs and capacity utilisation
- Employee productivity = output over a time period ÷ number of employees. Unit costs = total costs ÷ number of units of output. Capacity utilisation = actual output ÷ maximum possible output × 100.
- 7,200 units, 18 staff, total cost £28,800, capacity 9,000. Productivity, unit cost, utilisation?
- Productivity = 400 per employee. Unit cost = £4.00. Utilisation = 80%.
- Ways to increase productivity, and difficulties
- Training, motivation, better equipment, workflow changes, less waste, technology. Difficulties: costs come before gains, staff resistance, pressure on quality, extra output may not sell.
- Lean production in 7137
- Reducing inventory, re-works, waiting times and transportation times; kaizen (continuous small improvements suggested by staff); and standardised processes.
- Benefits and difficulties of JIT
- Benefits: lower holding costs, less storage, less cash tied up, less obsolete stock. Difficulties: needs reliable suppliers; delays stop output; no cover for demand spikes; lost bulk discounts.
- Network analysis: float time and the critical path
- Float time = latest finish time − duration − earliest start time. Example: LFT 9, duration 3, EST 4 → float 2 days. Activities with zero float form the critical path, which sets the shortest project time.
- Quality assurance vs checking finished goods
- Quality assurance builds quality into every stage to prevent faults. Checking finished goods only detects faults after they are made.
- Consequences of poor quality
- Returns, wasted materials, lost sales, damaged reputation, compensation, and low staff morale.
- Ways of matching output to demand in 7137
- Changing production scheduling; increasing or decreasing inventory; part-time, temporary, zero-hours or freelance staff; outsourcing; investment in capital and technology; increasing or decreasing capacity.
- Inventory turnover: formula and example
- Inventory turnover = cost of sales ÷ average inventories held. Cost of sales £300,000; inventory £22,000 at the start and £28,000 at the end, so average £25,000: turnover = 12 times a year.
- Economies and diseconomies of scale in 7137
- Economies (unit costs fall with size): technical, purchasing, financial. Diseconomies (unit costs rise with size): problems of control, communication and coordination.