OxfordAQA A-Level Business (9725): Inventory and supply chain management – Practice Questions

Original practice questions with full answers on inventory control charts, JIT versus JIC, sourcing and supply chain risk for OxfordAQA 9725 Business.

Subject
Business
Level
AS LEVEL
Topic
Topic 3 – Operational performance
Updated

Aligned to OxfordAQA A Level Business (9725), 9725 Version 1.1 (first teaching September 2026; first AS exams May/June 2027, first A-level exams May/June 2028). Official specification .

Syllabus page (what it covers and how it is assessed): OxfordAQA A Level Business.

Found an error? Report a correction.

Need help with this topic? Request a free trial class for A Level Business (9625 / 9725).

These are original questions written for Marlbridge, for revision and practice on this content. They are not reproduced past-paper questions, and they do not replicate the exam’s exact structure, question count or mark tariffs – examination boards hold copyright in their own papers. Use these alongside the official past papers from your board or school.

This set tests 3.2.1.3 Inventory and supply chain management from the OxfordAQA International AS and A-level Business (9725) specification, Version 1.1 (International AS, Unit 2). Section A has short-answer and calculation questions; Section B has longer, structured questions. Every business and figure is invented; inventory charts are given as tables. Revise first with the inventory and supply chain management study guide and the inventory and supply chain management revision notes.

Section A

1. Define the term buffer stock. [2]

2. Define the term lead time. [2]

3. Kelso Stationers sells 180 boxes of printer paper a week. It holds a buffer stock of 360 boxes, its maximum inventory level is 1,800 boxes, and the supplier’s lead time is 2 weeks. Calculate:

(a) the re-order level [2]

(b) the re-order quantity, assuming each delivery arrives as inventory reaches the buffer. [2]

4. Dunmore Tiles starts week 1 with 1,200 boxes of tiles (its maximum level). It sells 200 boxes a week. Its buffer stock is 200 boxes, its re-order level is 600 boxes, its re-order quantity is 1,000 boxes and the lead time is 2 weeks.

(a) Calculate Dunmore’s inventory at the end of each of weeks 1 to 4. [2]

(b) State the week at the end of which an order is placed, and the inventory level immediately after that order arrives. [2]

5. State two influences on the amount of inventory a business holds. [2]

6. Explain one advantage of just in time inventory management for a florist. [3]

7. Explain one reason why a chocolate maker might require its cocoa suppliers to hold third party accreditation. [3]

Section B

8. Dunmore Tiles (Question 4) learns that its supplier’s lead time will increase from 2 weeks to 3 weeks. Sales stay at 200 boxes a week and the re-order level stays at 600 boxes.

(a) Calculate Dunmore’s inventory at the end of week 6, just before the order placed at the end of week 3 arrives. [2]

(b) Calculate the re-order level Dunmore would need so that inventory does not fall below its buffer stock. [2]

(c) Explain one other way Dunmore could respond to the longer lead time. [2]

9. Fairlight Cases designs phone cases and buys them from manufacturers. It currently uses a single manufacturer. Analyse whether Fairlight should use several manufacturers instead. [6]

10. Marlowe Garments makes shirts from fabric imported by sea. A strike at the port delays fabric deliveries by four weeks. Explain two effects this supply chain issue could have on Marlowe. [4]

11. Explain two reasons why effective inventory control is valuable to a supermarket. [4]

12. Hartwell Engineering makes steel parts for agricultural machinery. It holds about six weeks of steel in inventory, which costs about $60,000 a year to store and insure. Its main steel supplier is 400 km away, and about one delivery in ten arrives late. Hartwell’s customers, machinery manufacturers, fine Hartwell for late deliveries. A consultant recommends switching to just in time, with daily deliveries of steel. Evaluate whether Hartwell should adopt just in time. [12]

Answers

1. The minimum level of inventory a business keeps [1] as a safety margin against late deliveries or unexpected demand [1]. [2]

2. The time between placing an order with a supplier [1] and receiving the goods [1]. [2]

3. (a) 360 + (180 × 2) [1] = 720 boxes [1].

(b) 1,800 − 360 [1] = 1,440 boxes [1]. [4]

4. (a) Week 1: 1,000; week 2: 800; week 3: 600; week 4: 400. All four correct [2] (two or three correct earns 1 mark).

(b) The order is placed at the end of week 3, when inventory reaches the re-order level of 600 [1]. It arrives at the end of week 5, when inventory has fallen to 200, so inventory rises to 200 + 1,000 = 1,200 boxes [1]. [4]

5. Any two of: how predictable demand is [1]; supplier lead time and reliability [1]; storage space and cost; whether goods perish or date; cash available; bulk discounts; whether the firm uses JIT or JIC. [2]

6. Flowers perish within days [1], so holding large stocks means many would wilt before being sold [1]. With JIT, fresh flowers arrive as orders come in, reducing waste and the cash tied up in stock [1]. [3]

7. Cocoa farming has been linked to concerns about child labour and deforestation, which customers may care about [1]. Independent accreditation gives evidence that suppliers meet labour and environmental standards [1], which supports the chocolate maker’s ethical marketing claims and reduces the risk of a damaging scandal [1]. [3]

8. (a) Weeks 4, 5 and 6 each use 200 boxes: 600 − (3 × 200) [1] = 0 boxes [1].

(b) 200 + (200 × 3) [1] = 800 boxes [1].

(c) Dunmore could increase its buffer stock [1], so that a late delivery or a busy week does not cause a stock-out, although this raises storage costs [1]. Alternatively, it could look for a supplier with a shorter lead time. [6]

Examiner insight: In part (a) the buffer has been used completely; any extra sales in those weeks would mean a stock-out. Saying so shows interpretation as well as calculation.

9. With one manufacturer, Fairlight is likely to get bulk discounts and a close relationship, which helps when launching new designs quickly [1]. But if that manufacturer has a breakdown or quality problem, Fairlight has no other source of cases [1], so it could miss a key season such as a new phone launch and lose sales [1]. Several manufacturers would spread this risk [1] and create competition that keeps prices down [1]. However, quality and colour may vary between manufacturers, and Fairlight would need more staff time to manage orders; a main manufacturer plus a back-up could balance cost and risk [1]. [6]

10. Production may stop once existing fabric runs out, leaving machinists idle while wages are still paid [1], which raises unit costs and lowers profit [1]. Marlowe may miss delivery dates for retailers’ new-season orders [1], damaging its reputation and risking lost future orders [1]. [4]

11. It prevents stock-outs of everyday products [1], so shoppers do not switch to rival supermarkets when items are missing [1]. It avoids holding too much perishable food [1], cutting waste and the cash tied up in inventory [1]. [4]

12. Credit chains of reasoning and a judgement, for example:

  • JIT would cut most of the $60,000 a year spent storing and insuring steel [1].
  • It would free cash now tied up in six weeks of inventory, which could fund other investment [1].
  • Less inventory means less space needed and less risk of steel being damaged in storage [1].
  • However, JIT needs reliable, nearby suppliers, and Hartwell’s supplier is 400 km away [1].
  • One delivery in ten already arrives late; with daily deliveries and almost no inventory, a late delivery would stop production that day [1].
  • Stopped production would make Hartwell late to its customers, triggering fines that could exceed the storage savings [1], and could cost it future contracts [1].
  • Daily deliveries over 400 km raise transport costs and may lose bulk-buying discounts [1].
  • Agricultural machinery demand is seasonal, so steady daily orders may not match Hartwell’s needs [1].
  • Hartwell could adopt JIT partly, cutting inventory from six weeks to one or two while keeping a buffer [1], or find a closer supplier first [1].
  • Judgement: Hartwell should not switch to full JIT yet, because its supplier is too distant and unreliable and late deliveries are penalised; it should reduce inventory gradually while improving supplier reliability [1]. [12]

Where marks are usually lost

  • Measuring lead time from the delivery back to the buffer rather than from the order.
  • Forgetting that a delivery adds the re-order quantity to whatever inventory remains.
  • Recommending more inventory without mentioning its cost.
  • Analysing single sourcing without linking the risk to the business’s own products or seasons.
  • Evaluating JIT without using the supplier’s distance and reliability given in the case.