Ten original OxfordAQA 9645 questions on sub-topic 3.3.4: analysis, design, the critical path, normal, boundary and erroneous test data, and evaluation.

Level
AS LEVEL
Topic
Topic 3 – Program design
Updated

Aligned to OxfordAQA A Level Computer Science (9645), 2024-onwards. Official specification .

Syllabus page (what it covers and how it is assessed): OxfordAQA A Level Computer Science.

Syllabus points this page covers

9645 (AS Level)

  • 3.3.4 Aspects of software development

This page covers 1 of the 4 subtopics in topic 3, Program design.

Found an error? Report a correction.

Need help with this topic? Request a free trial class for A Level Computer Science (9645).

These are original questions written for Marlbridge, for revision and practice on this content. They are not reproduced past-paper questions, and they do not replicate the exam’s exact structure, question count or mark tariffs – examination boards hold copyright in their own papers. Use these alongside the official past papers from your board or school.

These questions practise sub-topic 3.3.4 Aspects of software development of OxfordAQA International AS and A-level Computer Science (9645), Version 1.1: analysis, design, implementation, testing and evaluation. Code is Python.

Related pages: aspects of software development study guide · aspects of software development revision notes

Section A

1. Name the five aspects of software development in the order they are usually carried out. [2]

2. State what is meant by the critical path of a solution. [1]

3. Give two things that are produced at the design stage. [2]

4. State the three criteria used to evaluate a computer system. [3]

Section B

5. A school wants a program to record students’ attendance.

(a) Describe two ways in which the analyst could establish the requirements. [2]
(b) Explain why prototyping could help clarify the requirements. [2]
(c) State what a data model for this system would describe. [1]

6. A program accepts a pass mark entered as a whole number from 0 to 100 inclusive and shows “Pass” for 40 or more.

(a) Complete the table by giving the type of each test (normal, boundary or erroneous) and the expected outcome. [6]

Test data Type Expected outcome
72
40
39
101
“pass”

(b) Explain why 39 and 40 are both useful test values. [1]

7. The code below should accept only ages from 16 to 60 inclusive.

def valid_age(age):
    return age > 16 and age < 60

(a) State two test values that would show the code is wrong, and the result the code gives for each. [2]
(b) Write a corrected version of the function. [2]
(c) Explain why testing with only the value 30 would not have found the fault. [1]

8. A team builds an online ticket booking system. They plan to build the ticket search, the seat selection, the payment, a loyalty-points scheme and an email reminder service.

(a) Identify the part of this system that is most likely to be the critical path and justify your choice. [2]
(b) Explain one advantage of building the critical path first. [2]

9. A developer says: “Our program passed all the tests, so it has no errors.” Evaluate this statement. [3]

10. A company’s payroll program gives the right answers but takes 40 seconds to run, and no other programmer can understand the code.

(a) State which of the three evaluation criteria the program meets. [1]
(b) State which of the criteria it does not meet, giving evidence for each. [4]

Answers

1. Analysis, design, implementation, testing, evaluation [2 marks: all five in order [2]; four in order [1]]. [2]

2. The part of the solution that everything else depends upon [1]. [1]

3. Any two [1 each]: data structures for the data model; algorithms; a modular structure (such as a hierarchy chart); the user interface design. [2]

4. Correctness [1]; efficiency [1]; maintainability [1]. [3]

5. (a) Any two [1 each]: interview teachers and office staff; give them questionnaires; observe how attendance is currently recorded; examine the existing forms.
(b) A prototype is a rough working model that users can try [1]; seeing it helps them say what is missing or wrong, so requirements become clearer [1]. [2]
(c) The data to be stored (such as student, date, present or absent) and how items relate [1]. [1]

6. (a)

Test data Type Expected outcome
72 Normal Accepted; shows “Pass”
40 Boundary Accepted; shows “Pass”
39 Boundary Accepted; shows “Fail”
101 Boundary (just above range) Rejected
“pass” Erroneous Rejected, with no crash

Each correct type [3 marks for the five types: 5 correct [3]; 3 or 4 correct [2]; 1 or 2 correct [1]] and each correct outcome [3 marks, same scale]. Accept 101 as erroneous; accept 39 described as the value just below the pass boundary. [6] (b) They sit either side of the pass boundary, so they show whether the condition uses >= rather than > [1]. [1]

7. (a) 16 returns False [1] and 60 returns False [1], although both should be accepted. [2]
(b) return age >= 16 and age <= 60 [2: >= for the lower limit [1]; <= for the upper limit [1]]. [2]
(c) 30 is in the middle of the range and gives True for both versions, so it does not test the boundaries [1]. [1]

Examiner insight: the code gives False for 16 because 16 > 16 is False, and False for 60 because 60 < 60 is False.

8. (a) Payment together with ticket search and seat selection, or the booking process as a whole (search, select seat, pay) [1]; the loyalty scheme and email reminders both depend on a completed booking [1]. [2]
(b) Any one advantage with explanation [2]: the most important part is tested early [1], so serious problems are found before other features rely on it [1]; or the later features are added to a working base [1], so the team always has something that works [1]. [2]

9. The statement is not necessarily true [1]. Testing can show that errors are present but cannot prove that none exist, because not every possible input can be tried [1]; the tests might not have included boundary or erroneous data or covered every requirement [1]. [3]

10. (a) Correctness (the answers are right) [1]. [1]
(b) Efficiency: it takes 40 seconds to run, which suggests wasted time or resources [2: not met [1]; evidence [1]]. Maintainability: no other programmer can understand the code, so it cannot easily be changed (poor names, no comments or structure) [2: not met [1]; evidence [1]]. [4]

Frequently asked questions

Is a boundary test the same as an erroneous test? No. A boundary test is at the edge of the range (and just outside it); erroneous data is invalid for other reasons, such as the wrong type.

Do I need to know a particular agile method? No. The specification only expects awareness of a prototyping or agile approach and its focus on solving the critical path first.

Official syllabus

OxfordAQA International AS and A-level Computer Science (9645) specification, Version 1.1, for International AS exams May/June 2025 onwards and International A-level exams May/June 2026 onwards: sub-topic 3.3.4 Aspects of software development.

Related resources

Get free revision emails (optional)

Occasional emails with practice questions, worked explanations and links to free resources for the qualification and subjects you choose. No spam, and you can unsubscribe from any email. The free tools on this site never need an email.