AQA A-Level Business (7132): Analysing operational performance – Practice Questions

Original practice questions with mark-scheme answers on labour productivity, unit costs, capacity and capacity utilisation for AQA A-level Business 7132.

Subject
Business
Level
A LEVELS
Topic
Operational management
Updated

Aligned to AQA A Level Business (7132), For first teaching from September 2023. Official specification .

Syllabus page (what it covers and how it is assessed): AQA A Level Business.

Syllabus points this page covers

7132

  • 3.4.2 Analysing operational performance

This page covers 1 of the 5 subtopics in topic 4, Operational management.

Found an error? Report a correction.

Need help with this topic? Request a free trial class for A Level Business (7132).

These are original questions written for Marlbridge, for revision and practice on this content. They are not reproduced past-paper questions, and they do not replicate the exam’s exact structure, question count or mark tariffs – examination boards hold copyright in their own papers. Use these alongside the official past papers from your board or school.

These questions cover section 3.4.2 Analysing operational performance of the AQA A-level Business (7132) specification. All businesses and figures are invented. Revise first with the operational performance study guide and the operational performance revision notes.

Section A: Short-answer questions

1. A factory produced 36,000 units in a month. Its maximum capacity is 45,000 units. What is its capacity utilisation? [1]

A: 20%

B: 80%

C: 125%

D: 9,000%

2. A team of 30 workers produces 2,400 units in a week. What is the labour productivity? [1]

A: 8 units per worker

B: 80 units per worker

C: 72,000 units per worker

D: 2,430 units per worker

3. Define the term “unit cost”. [2]

4. Explain one reason why a business might choose to operate below 100% capacity utilisation. [3]

5. Kestrel Candles produced 20,000 candles last month with 16 employees. Its maximum capacity is 25,000 candles a month. Fixed costs are £15,000 a month and variable costs are £1.50 per candle.

(a) Calculate the labour productivity (candles per employee). [1]

(b) Calculate the unit cost. [3]

(c) Calculate the capacity utilisation. [1]

6. This month Kestrel produces 24,000 candles with the same 16 employees.

(a) Calculate the new unit cost, to the nearest penny. [2]

(b) Explain why the unit cost has fallen. [2]

7. Labour productivity at Kestrel was 1,250 candles per employee last month. Six months later it is 1,100. Calculate the percentage change. [2]

Section B: Structured questions

8. Analyse two possible causes of a fall in labour productivity at a manufacturing business. [6]

9. Kestrel Candles is now operating at 96% capacity utilisation and demand is still rising. Assess whether it should invest in extra capacity. [9]

10. A retailer asks Kestrel to make an extra 5,000 candles at £2.60 each, in a month when output would otherwise be 20,000. Analyse how Kestrel’s cost data could help it decide whether to accept the order. [6]

11. Explain two limitations of using operations data to judge a business’s performance. [4]

12. Evaluate whether labour productivity is the best measure of the operational performance of a business. [12]

Answers

1. B [1]. 36,000 ÷ 45,000 × 100 = 80%. [1]

2. B [1]. 2,400 ÷ 30 = 80. [1]

3. The average cost of producing one unit of output [1], found by dividing total costs by the number of units produced [1]. [2]

4. Spare capacity allows the business to cope with unexpected extra orders or seasonal peaks [1], so it avoids turning customers away or paying for overtime [1]. It also leaves time for maintenance and reduces the risk of machine breakdown, which protects quality and delivery dates [1]. [3]

5. (a) 20,000 ÷ 16 = 1,250 candles per employee [1].

(b) Variable costs = 20,000 × £1.50 = £30,000 [1]. Total cost = £15,000 + £30,000 = £45,000 [1]. Unit cost = £45,000 ÷ 20,000 = £2.25 [1].

(c) 20,000 ÷ 25,000 × 100 = 80% [1]. [5]

6. (a) Total cost = £15,000 + 24,000 × £1.50 = £51,000 [1]. Unit cost = £51,000 ÷ 24,000 = £2.13 (£2.125) [1].

(b) Fixed costs of £15,000 do not change [1], so they are spread over more candles, and each candle carries a smaller share of fixed costs, even though variable cost per candle is unchanged [1]. [4]

7. (1,100 − 1,250) ÷ 1,250 [1] × 100 = −12%, a fall of 12% [1]. [2]

8. Cause 1: lower motivation or morale [1]. If staff feel undervalued or are worried about job security, they may work less effectively and be absent more often [1], so fewer units are produced per worker [1]. Cause 2: out-of-date equipment or poor training [1]. Machines that break down or workers who do not know new methods slow production [1], which reduces output per employee, especially if the business has recently taken on new staff [1]. Credit also: poor management and scheduling; shortages of materials. [6]

9. For: at 96% there is little spare capacity, so rising demand means turned-away orders or late deliveries [1]. Extra capacity would let Kestrel meet more orders and increase revenue [1]. Higher output could lower unit cost because fixed costs are spread more widely [1]. Against: investment is costly and may raise fixed costs [1]. If the rise in demand is temporary or seasonal, the new capacity could be under-used [1]. Alternatives exist, such as overtime, extra shifts or outsourcing [1]. The business must have the finance and space to expand [1]. Judgement: investing is sensible if forecasts show that demand is likely to stay high for several years [1]; otherwise, short-term measures such as overtime or subcontracting may be lower risk, and the decision should be reviewed against sales data [1]. [9]

10. Fixed costs of £15,000 are already covered by the normal 20,000 candles [1]. The extra order brings only extra variable costs of 5,000 × £1.50 = £7,500 [1], while the revenue is 5,000 × £2.60 = £13,000, so it adds £5,500 to profit [1]. The average unit cost at 25,000 candles is (£15,000 + £37,500) ÷ 25,000 = £2.10, which is below the price of £2.60 [1]. The order would take Kestrel to its full capacity of 25,000, leaving no flexibility for other customers [1]. It should check that regular customers will not be let down and that the lower price will not become a benchmark for other buyers [1]. [6]

11. Limitation 1: data is based on averages [1], which can hide differences between shifts or products, so problems in one area may go unnoticed [1]. Limitation 2: figures are about the past [1] and measure quantity, not quality; a business could raise productivity while errors and complaints increase [1]. Accept: data may be for an unrepresentative period; allocation of fixed costs is a judgement. [4]

12. For: labour productivity is simple to calculate and easy to compare over time and between firms [1]. It links directly to costs, because higher output per worker lowers labour cost per unit [1]. It shows the effect of training, motivation and methods [1]. It helps with staffing plans [1]. Against: it ignores quality, so productivity could rise while errors grow [1]. It does not show capital efficiency; a firm with robots may have high labour productivity but a large investment [1]. It ignores other objectives such as flexibility, speed of response and environmental impact [1]. It does not show whether the products are what customers want [1]. Other measures, such as unit cost, capacity utilisation, defect rate and delivery time, give a fuller view [1]. Factors: the type of business, since labour-intensive services depend more on staff output than a highly automated plant [1]. Judgement: labour productivity is a useful measure but not the best on its own; it should be combined with unit cost and a quality measure, chosen to fit the business’s operational objectives [1]. Customer satisfaction should also be considered [1]. [12]

Examiner insight: Always state the unit, and say what each figure means for the business rather than leaving it as a number.

Where marks are usually lost

  • Leaving fixed costs out of total cost.
  • Forgetting to multiply by 100 for capacity utilisation.
  • Giving a percentage change without a sign or direction.
  • Treating 100% utilisation as always desirable.
  • Not interpreting the calculation.
  • Judging performance from productivity alone, with no comment on quality.