AQA A-Level Business (7132): Analysing operational performance – Revision Notes

Condensed recall for AQA A-level Business 7132 section 3.4.2: labour productivity, unit cost, capacity and capacity utilisation formulas, interpretation and a self-test.

Subject
Business
Level
A LEVELS
Topic
Operational management
Updated

Aligned to AQA A Level Business (7132), For first teaching from September 2023. Official specification .

Syllabus page (what it covers and how it is assessed): AQA A Level Business.

Syllabus points this page covers

7132

  • 3.4.2 Analysing operational performance

This page covers 1 of the 5 subtopics in topic 4, Operational management.

Found an error? Report a correction.

Need help with this topic? Request a free trial class for A Level Business (7132).

Condensed notes on section 3.4.2 Analysing operational performance of AQA A-level Business (7132, for first teaching from September 2023). The full explanations and the Marsden Ceramics worked example are in the operational performance study guide; exam-style questions are in the operational performance practice set.

Specification content

  • The interpretation, calculation and use of operations data in operational decision making and planning.
  • You should be able to calculate: labour productivity; unit costs (average costs); capacity; capacity utilisation.

Key terms

Term Meaning
Labour productivity Output per worker (or per hour) in a period
Unit cost (average cost) Total cost divided by total output
Fixed costs Costs that do not change with output in the short run
Variable costs Costs that change with output
Capacity Maximum output possible in a period with existing resources
Capacity utilisation Actual output as a percentage of maximum output
Under-utilisation Using much less than full capacity
Benchmarking Comparing performance with rivals or best practice

Formulas

Measure Formula
Labour productivity total output ÷ number of employees
Labour productivity per hour total output ÷ total hours worked
Total cost fixed costs + (variable cost per unit × output)
Unit cost total cost ÷ output
Capacity utilisation (%) actual output ÷ maximum output × 100
Spare capacity maximum output − actual output

Always give the unit (units per worker, £ per unit, %).

Worked example to remember

Output 48,000 plates a month; capacity 60,000; 60 employees working 160 hours each; fixed costs £90,000; variable cost £3 per plate.

  • Productivity: 48,000 ÷ 60 = 800 per employee; hours = 9,600, so 5 per hour.
  • Total cost: £90,000 + 48,000 × £3 = £234,000; unit cost = £4.875.
  • Capacity utilisation: 48,000 ÷ 60,000 × 100 = 80%.
  • Output rises to 54,000: productivity 900; total cost £252,000; unit cost £4.67; utilisation 90%.
  • At 60,000: total cost £270,000; unit cost £4.50.

Why unit cost falls: the same fixed costs are spread over more units.

Second worked example: reading two years of data

Year 1 Year 2
Output 3,600 3,780
Employees 12 14
Maximum capacity 4,800 4,800
Total costs £288,000 £321,300
  • Productivity: 3,600 ÷ 12 = 300; 3,780 ÷ 14 = 270, a fall of 10%.
  • Unit cost: £288,000 ÷ 3,600 = £80; £321,300 ÷ 3,780 = £85, a rise of 6.25%.
  • Utilisation: 3,600 ÷ 4,800 = 75%; 3,780 ÷ 4,800 = 78.75%.
  • Reading: output rose 5% but staff rose by two, so productivity fell and unit cost rose. Spare capacity remains. Possible causes: staff hired ahead of demand or not yet trained. The numbers raise the question; they do not answer it alone.

Interpreting capacity utilisation

Level Meaning Consequences
Low Under-utilised High unit costs; wasted resources; scope for new orders
About 80 to 90% Efficient with some flexibility Lower unit costs; can handle small extra demand
100% Full capacity No flexibility; risk of late delivery, breakdown, turned-away orders; overtime or outsourcing costs

No single “ideal” figure: depends on whether demand is steady or seasonal and on the cost of failing to supply.

Interpreting productivity and unit costs

  • Compare over time, against rivals and against targets.
  • Falling productivity: poor morale, absence, weak training, old equipment, inexperienced workers.
  • Rising unit cost: higher material prices, lower output (fixed costs spread thinner), wage rises, waste.
  • If wages rise by less than productivity, labour cost per unit falls.

Using the data

  • Capacity: high utilisation suggests investing; low suggests closing a line or finding new customers.
  • Staffing: productivity shows workers needed for a given output.
  • Pricing and orders: unit cost is a floor for price; check an order’s price against it.
  • Improvement: trends and benchmarks show where to focus.

Limits of the data

  • Averages hide variation between shifts or products.
  • Productivity measures quantity, not quality.
  • Allocating fixed costs between products is a judgement.
  • Data is historical; short periods may mislead.
  • Automation can raise labour productivity while adding capital cost.

Exam traps

  • Unit cost is total cost divided by output, including fixed costs.
  • Multiply by 100 for capacity utilisation.
  • 100% utilisation is not always best.
  • Match the productivity measure (per worker or per hour) to the data.
  • Always interpret the number you calculate.

Self-test

  1. Define “capacity utilisation”.
  2. A firm makes 7,500 units with 25 workers. Calculate labour productivity.
  3. Its fixed costs are £12,000 and variable costs are £4 per unit. Calculate total cost at 7,500 units.
  4. Calculate unit cost at 7,500 units.
  5. Its maximum capacity is 10,000 units. Calculate capacity utilisation.
  6. Output rises to 9,000 units. Calculate the new unit cost.
  7. Explain why unit cost fell in question 6.
  8. Give two consequences of operating at 100% capacity.
  9. Labour productivity falls from 120 to 108 units per worker. Calculate the percentage change.
  10. Give two possible causes of falling productivity.
  11. Give one limitation of using productivity data alone to judge performance.
  12. A firm has capacity of 50,000 units and spare capacity of 12,000 units. Calculate capacity utilisation.

Answers

  1. Actual output as a percentage of the maximum possible output.
  2. 7,500 ÷ 25 = 300 units per worker.
  3. £12,000 + (7,500 × £4 = £30,000) = £42,000.
  4. £42,000 ÷ 7,500 = £5.60.
  5. 7,500 ÷ 10,000 × 100 = 75%.
  6. Total cost = £12,000 + 9,000 × £4 = £48,000; unit cost = £48,000 ÷ 9,000 = £5.33 (to two decimal places).
  7. Fixed costs of £12,000 are spread over more units.
  8. Any two: no flexibility; late deliveries or turned-away orders; risk of breakdown; staff stress; overtime or outsourcing costs.
  9. (108 − 120) ÷ 120 × 100 = −10%, a fall of 10%.
  10. Any two: low morale; absence; poor training; old equipment; inexperienced workers.
  11. Productivity measures quantity, not quality; or it hides variation between shifts or products.
  12. Actual output = 50,000 − 12,000 = 38,000; 38,000 ÷ 50,000 × 100 = 76%.