Practice Questions
AQA A-Level Business (7132): Managing strategic implementation – Practice Questions
Original practice questions with mark-scheme answers on leadership, communication, structure and network analysis with critical path and float for AQA A-level Business 7132.
- Subject
- Business
- Level
- A LEVELS
- Topic
- Managing strategic change
- Author
- Marlbridge Academic Team
- Updated
- Reviewed by
- Salman Ahmad (what this means)
Aligned to AQA A Level Business (7132), For first teaching from September 2023. Official specification .
Syllabus page (what it covers and how it is assessed): AQA A Level Business.
Syllabus points this page covers
7132
- 3.10.3 Managing strategic implementation
This page covers 1 of the 4 subtopics in topic 10, Managing strategic change.
Found an error? Report a correction.
Need help with this topic? Request a free trial class for A Level Business (7132).
These are original questions written for Marlbridge, for revision and practice on this content. They are not reproduced past-paper questions, and they do not replicate the exam’s exact structure, question count or mark tariffs – examination boards hold copyright in their own papers. Use these alongside the official past papers from your board or school.
These questions cover section 3.10.3 managing strategic implementation of the AQA A-level Business (7132) specification. All businesses and figures are invented. Revise first with the study guide and the revision notes.
Questions 6 to 10 use this data. Halbury Foods is launching a new product range. The activities, durations in weeks and dependencies are:
| Activity | Duration | Must follow |
|---|---|---|
| A: Market research | 2 | none |
| B: Develop recipes | 5 | none |
| C: Design packaging | 4 | A |
| D: Source ingredients | 3 | B |
| E: Set up production line | 6 | A, B |
| F: Print packaging | 2 | C, D |
| G: Trial production | 3 | E |
| H: Launch | 2 | F, G |
Section A: Short-answer questions
1. An activity has an earliest start time of 5 weeks, a duration of 3 weeks and a latest finish time of 12 weeks. What is its total float? [1]
A: 2 weeks
B: 4 weeks
C: 7 weeks
D: 9 weeks
2. Which one of the following is most likely to suit an autocratic leadership style? [1]
A: A team of highly skilled specialists in a research laboratory
B: An urgent crisis requiring a quick decision
C: A creative design team seeking new ideas
D: A long-term plan that depends on staff commitment
3. Define “critical path”. [2]
4. State two reasons why communication is important when implementing a new strategy. [2]
5. Explain one problem a tall organisational structure can cause for strategic implementation. [3]
Section B: Structured questions
6. Calculate the earliest start time for each of activities A to H. [4]
7. Calculate the minimum time to complete the project, and identify the critical path. [4]
8. Calculate the total float for activities A, C, D and F. [4]
9. Activity E takes 9 weeks instead of 6. State the new project duration and explain what has happened to the critical path. [3]
10. Halbury can reduce trial production (G) to 2 weeks by hiring extra staff. Explain whether this would speed up the launch, and by how much, assuming E takes 6 weeks. [3]
11. Analyse why a democratic leadership style might help Halbury implement its new strategy, and one reason why it might not. [6]
12. Evaluate the usefulness of network analysis for a business implementing a major strategy. [12]
Answers
1. B [1]. Total float = LFT − duration − EST = 12 − 3 − 5 = 4 weeks. [1]
2. B [1]. In a crisis speed matters and an autocratic style allows quick decisions. [1]
3. The longest path through the network [1], which determines the shortest time in which the project can be completed (activities on it have no float) [1]. [2]
4. Any two: it explains the strategy and reasons to staff [1]; it reduces uncertainty and resistance [1]; it co-ordinates departments [1]; it gives feedback on progress and problems [1]. [2]
5. In a tall structure, messages pass through many layers [1], so they are slow and may be distorted or lost [1], which delays decisions and the implementation of the strategy, and managers at the top may lose touch with what is happening [1]. [3]
6. A: 0, B: 0 [1]. C: 2, D: 5 [1]. E: 5 (must wait for B), F: 8 (waits for D, which ends at 8, and C, which ends at 6) [1]. G: 11, H: 14 (waits for G, which ends at 14, and F, which ends at 10) [1]. [4]
7. Earliest finish times: A 2, B 5, C 6, D 8, E 11, F 10, G 14, H 16 [1]. The minimum project time is 16 weeks [1]. The critical path is B, E, G, H [1]: 5 + 6 + 3 + 2 = 16 [1]. [4]
8. Latest finish times: H 16, G 14, F 14, E 11, D 12, C 12, B 5, A 5. A: 5 − 2 − 0 = 3 [1]. C: 12 − 4 − 2 = 6 [1]. D: 12 − 3 − 5 = 4 [1]. F: 14 − 2 − 8 = 4 [1]. [4]
9. E would finish at 5 + 9 = 14 [1], so G finishes at 17 and the project takes 19 weeks [1]. The critical path remains B, E, G, H, but it is now longer, and all other activities have more float [1]. [3]
10. With E at 6 weeks, G could start at 11 and finish at 13 [1]. Launch H could then start at 13 and the project would take 15 weeks, one week quicker [1]. The saving is only one week because B, E, G, H is still critical, and the other paths are shorter (the next longest, B, D, F, H, takes only 12 weeks) [1]. [3]
11. Democratic style: involving managers and staff in planning the launch gives access to their knowledge of production, packaging and customers [1], which improves the plans [1]. Staff who help to shape the plan are more committed to it and less likely to resist [1]. Against: consultation takes time [1], which could delay a launch with a fixed deadline [1], and different views may cause disagreement, so an autocratic or mixed approach may be needed if time is short [1]. [6]
12. For: network analysis shows the minimum completion time and the critical activities [1], so managers focus attention where delay would matter [1]. It shows float, so resources can move from non-critical to critical tasks [1]. It shows dependencies clearly and helps co-ordination [1]. It allows quick re-planning when something changes [1]. Against: it relies on accurate estimates of time, which are hard for new strategies [1]. It ignores costs unless extended, and speeding up work may cost more [1]. Complex strategies have too many activities for a simple diagram [1]. It does not deal with the people side of implementation, such as motivation and resistance [1]. Factors: the size and complexity of the project, the reliability of the estimates, and whether it is used with other tools such as budgets and good leadership [1]. Judgement: network analysis is very useful for the timing of well-understood projects [1], but it cannot make a strategy succeed on its own, as leadership, communication and structure also matter [1]. [12]
Examiner insight: In network questions, show the forward and backward pass, then say what the critical path and float mean for decisions.
Where marks are usually lost
- Choosing the shortest path as the critical path.
- Forgetting to subtract the duration when calculating float.
- Saying a shorter non-critical activity speeds up the project.
- Describing communication as one-way.
- Recommending a leadership style with no link to the situation.
Related resources
-
Revision notes
AQA A-Level Business (7132): Managing strategic implementation – Revision Notes
Condensed recall for AQA A-level Business 7132 section 3.10.3: leadership, communications, structure and network analysis with critical path and total float.
Business · AQA · A Level
Revise topic -
Study guides
AQA A-Level Business (7132): Problems with strategy and why strategies fail
Study guide to AQA A-level Business 7132 section 3.10.4: difficulties of strategy, planned versus emergent strategy, strategic drift, evaluating performance, planning and crisis management.
Business · AQA · A Level
Read guide -
Practice questions
AQA A-Level Business (7132): Problems with strategy and why strategies fail – Practice Questions
Original practice questions with mark-scheme answers on strategic drift, planned and emergent strategy, evaluating performance and contingency planning for AQA A-level Business 7132.
Business · AQA · A Level