AQA A-Level Business (7132): Managing strategic implementation – Revision Notes

Condensed recall for AQA A-level Business 7132 section 3.10.3: leadership, communications, structure and network analysis with critical path and total float.

Subject
Business
Level
A LEVELS
Topic
Managing strategic change
Updated

Aligned to AQA A Level Business (7132), For first teaching from September 2023. Official specification .

Syllabus page (what it covers and how it is assessed): AQA A Level Business.

Syllabus points this page covers

7132

  • 3.10.3 Managing strategic implementation

This page covers 1 of the 4 subtopics in topic 10, Managing strategic change.

Found an error? Report a correction.

Need help with this topic? Request a free trial class for A Level Business (7132).

Condensed notes on section 3.10.3 Managing strategic implementation of AQA A-level Business (7132, for first teaching from September 2023). Section 3.10 is A-level only. The nine-activity store opening network is in the study guide; questions are in the practice set.

Specification content

  • How to implement strategy effectively: the value of leadership and of communications.
  • The importance of organisational structure in strategic implementation.
  • The value of network analysis: understanding and interpreting network diagrams, amending them, identifying the critical path and total float.

Key terms

Term Meaning
Implementation Turning a strategic decision into action
Leadership Ability to influence and direct others towards a goal
Two-way communication Messages and feedback flowing in both directions
Network analysis Planning a project by showing activities, durations and order
Critical path The longest path; it sets the project duration
Earliest start time (EST) Earliest an activity can begin
Latest finish time (LFT) Latest an activity can end without delaying the project
Total float Delay possible without delaying the project

Leadership

Sets direction; motivates; decides; allocates resources; models behaviour; builds support.

Style Suits
Autocratic Crisis; inexperienced staff; speed
Democratic Skilled staff; need for commitment and ideas
Laissez-faire Expert, self-motivated staff
Paternalistic Staff needing reassurance

Limits: over-dependence on one leader; leadership alone is not enough.

Communications

Explain the strategy; reduce resistance; co-ordinate departments; give feedback; build commitment. Problems: distortion through layers; overload; inconsistent messages; poor listening; missing remote or shift workers. Good practice: one clear message, repeated through several channels, with a way to respond.

Structure

Feature Effect
Tall against flat Tall slows communication; flat speeds decisions but loads managers
Centralised against decentralised Control against speed and local response
Functional against product or region Expertise against fit with diversification or expansion
Project teams or matrix Cross-department change; reporting lines may blur
Clear accountability Someone owns each action

Network analysis: method

  1. Forward pass: EST = largest earliest finish of preceding activities; EFT = EST + duration.
  2. Backward pass: LFT of last activity = project duration; LFT of earlier activity = smallest latest start of the activities that follow; latest start = LFT − duration.
  3. Total float = LFT − duration − EST.
  4. Critical path: zero-float activities; the longest path.

Worked mini-example

Activity Duration Follows
A 3 none
B 2 none
C 4 A
D 5 A, B
E 2 C, D

EST: A 0, B 0, C 3, D 3, E 8 (D finishes at 8; C at 7). Project duration = 10. LFT: E 10, D 8, C 8, B 3, A 3. Float: A 0; B 3 − 2 − 0 = 1; C 8 − 4 − 3 = 1; D 0; E 0. Critical path: A, D, E (3 + 5 + 2 = 10).

Amending a network

  • Change the duration, then repeat the passes.
  • Shortening a critical activity shortens the project (until another path becomes critical).
  • Shortening a non-critical activity saves nothing overall.
  • A delay longer than an activity’s float delays the project.

Value and limits of network analysis

Value Limits
Shortest time; focus on critical tasks Depends on accurate time estimates
Highlights float for resource use Costs ignored unless added
Clear dependencies; easy to re-plan Large networks complex
Basis for monitoring Ignores motivation and people issues

Model analysis paragraph

“The critical path is B, D, F, I, so a delay to shopfitting delays the opening of the store. Recruiting the manager has two weeks of float, so it can slip without affecting the opening. The manager should therefore focus resources on the critical activities and keep a close eye on any that use up their float. The network is only as reliable as the estimates, so the plan should be reviewed regularly.”

Command words

  • Calculate: show the forward and backward pass, state the float and the critical path.
  • Evaluate: judge the usefulness of leadership, communication, structure and network analysis for the case.

Exam traps

  • The critical path is the longest path.
  • Float = LFT − duration − EST (do not forget the duration).
  • Use the project duration as the LFT for the final activity.
  • Shortening non-critical activities does not speed up the project.
  • Link leadership style to the situation, not to a fixed “best” style.

Self-test

  1. Define “critical path”.
  2. State the formula for total float.
  3. An activity has EST 6, duration 4 and LFT 12. Calculate the total float.
  4. What does zero float mean?
  5. In the mini-example, what is the effect of C taking 6 weeks instead of 4?
  6. Give two reasons communication matters in implementation.
  7. Give one problem of tall hierarchies for communication.
  8. When is an autocratic style appropriate?
  9. Give one limit of network analysis.
  10. Why does shortening a non-critical activity not shorten the project?
  11. Give one structural change that could suit expansion into overseas markets.
  12. Why is two-way communication better than one-way during change?

Answers

  1. The longest path through the network; it determines the project duration.
  2. Total float = LFT − duration − EST.
  3. 12 − 4 − 6 = 2 weeks.
  4. The activity is critical: any delay to it delays the whole project.
  5. C would finish at 9 (3 + 6) instead of 7, so E starts at 9 and the project takes 11 weeks; C is now critical (float was only 1).
  6. Any two: explain the strategy; reduce resistance; co-ordinate; give feedback; build commitment.
  7. Messages become slow or distorted as they pass through many layers.
  8. In a crisis, when speed is vital or staff are inexperienced.
  9. Any one: depends on accurate estimates; ignores cost unless added; complex for large projects; ignores people issues.
  10. Because the critical path still sets the end date; the longest path is unchanged.
  11. For example, a regional structure with local decision-making.
  12. It lets staff ask questions and raise problems, which reduces misunderstanding and gives managers feedback to adjust the plan.