Practice Questions
Cambridge A Level Information Technology (ICT): 16.8 Methods of software development (9626) – Practice Questions
Original practice questions with marked answers on waterfall, iterative, incremental, RAD and agile software development for section 16.8 of Cambridge A Level IT 9626.
- Subject
- ICT
- Level
- A LEVEL
- Topic
- System life cycle
- Author
- Marlbridge Academic Team
- Updated
- Reviewed by
- Harris Khan (what this means)
Aligned to Cambridge A Level Information Technology (9626), 2025-2027. Official specification .
Syllabus page (what it covers and how it is assessed): Cambridge A Level Information Technology.
Syllabus points this page covers
9626 (A Level)
- 16.8 Methods of software development
This page covers 1 of the 10 subtopics in topic 16, System life cycle.
Found an error? Report a correction.
Need help with this topic? Request a free trial class for A Level Information Technology (9626).
These are original questions written for Marlbridge, for revision and practice on this content. They are not reproduced past-paper questions, and they do not replicate the exam’s exact structure, question count or mark tariffs – examination boards hold copyright in their own papers. Use these alongside the official past papers from your board or school.
These questions cover section 16.8 Methods of software development of the Cambridge International AS & A Level Information Technology 9626 syllabus for examination in 2025, 2026 and 2027 (version 4). This is A Level only content examined in Paper 3 (Advanced Theory), where calculators are not allowed. All questions can be answered on paper.
Revise first with the study guide and revision notes. The Cambridge A Level IT hub lists every topic.
Questions
1. State the five methods of software development named in the syllabus. [5]
2. Describe how the waterfall method works. [3]
3. Give two advantages and two disadvantages of the waterfall method. [4]
4. Explain the difference between iterative development and incremental development. [3]
5. A software company is building a booking system for a chain of 20 gyms. The system will have separate modules for class bookings, membership payments and equipment maintenance. The class booking module is needed first.
(a) Explain why incremental development is suitable. [2]
(b) Describe how the system would be developed using this method. [3]
(c) Give one disadvantage of using this method here. [1]
6. A start-up is building a mobile app to help runners find routes. The founders are not sure which features users will want and expect to change their plans often. They can meet the developers every week.
(a) Describe how agile development would work for this project. [3]
(b) Explain why waterfall would be unsuitable. [2]
(c) Give one disadvantage of agile for this project. [1]
7. Describe the main features of rapid application development (RAD). [3]
8. A college needs an internal tool for room bookings within six weeks. Several teachers are willing to help design it.
Evaluate the use of RAD for this project. [4]
9. A company is developing the control software for a hospital’s infusion pump. The rules are laid down by law and cannot change. Any fault could harm a patient.
Evaluate waterfall and agile for this project, and recommend a method. [6]
Answers
1. Agile [1]; iterative [1]; incremental [1]; rapid application development (RAD) [1]; waterfall. [1] [5]
2. The stages (requirements or analysis, design, build, test, implementation, maintenance) are carried out one after another in a fixed order [1]; each stage is completed and signed off before the next one begins [1]; there is little or no going back to an earlier stage. [1] [3]
3. Advantages (any two): simple to understand and manage; clear milestones and documents; easy to plan cost and time; suits clear, fixed requirements. [1 each] Disadvantages (any two): hard to change requirements once a stage is complete; users see the system only at the end; early mistakes are found late and cost more to fix; slow to deliver any benefit. [1 each] [4]
4. Iterative development builds a rough version of the whole system and then repeats the cycle to refine and improve it [1]; incremental development splits the system into parts and builds and delivers each part in turn, adding it to the earlier ones [1]; so iterative refines the whole, while incremental adds finished parts. [1] [3]
5. (a) The system divides into independent modules [1], and the class booking module is needed first, so it can be delivered and used early. [1] [2]
(b) Build, test and deliver the class booking module first [1]; then build and deliver the membership payments module and then the equipment maintenance module in turn [1]; each is added to the system and tested together with the earlier ones. [1] [3]
(c) Any one: the modules must be designed to fit together, which needs overall planning at the start; integration work is needed; the complete system takes longer. [1] [1]
6. (a) Work is done in short sprints of one to four weeks [1]; at the start of each sprint the team and founders choose features from a prioritised list, and the team delivers working software at the end [1]; the founders give feedback at the weekly meetings and can change the priorities for the next sprint. [1] [3]
(b) In waterfall the requirements and design are fixed before building starts [1], so it is hard to change when the founders change their plans, and users would see nothing until the end. [1] [2]
(c) Any one: the final cost, time and feature list are hard to predict; needs constant involvement from the founders; less documentation. [1] [1]
7. Any three: quick prototypes are built and refined [1]; users take a strong part in the design, for example in workshops [1]; reusable components and development tools are used to speed up construction [1]; work is time-boxed with fixed short deadlines [1]. [3]
8. Suitable (up to 2 marks): fast delivery fits the six-week limit [1]; the teachers’ involvement fits RAD’s use of user workshops and prototypes, so the tool will suit their needs. [1] Less suitable (up to 1 mark): the teachers have to be available, which takes time from teaching; quality and documentation may suffer. [1] Judgement (1 mark): for example RAD is a good fit because the tool is small, internal and not critical. [1] Maximum 4. [4]
9. Waterfall (up to 2 marks): suits fixed requirements and gives full documentation and sign-off of each stage, which helps in checking safety [1]; but changes are hard, and users see the system only at the end, so mismatches show late. [1] Agile (up to 2 marks): fast, flexible, with frequent feedback [1]; but less documentation, and the cost and final features are harder to predict, which is a problem for a safety-critical, regulated device. [1] Link to the scenario (1 mark): the rules are fixed by law, so the flexibility of agile is not needed, and a fault could harm patients, so thorough documentation and checking at each stage are essential. [1] Recommendation (1 mark): waterfall, justified. [1] Maximum 6. [6] Examiner insight: “Evaluate” needs a clear recommendation based on the scenario. An answer that lists points about both methods and stops will not reach full marks.
Where marks are usually lost
- Confusing iterative with incremental.
- Giving “it is quick” as a reason for several different methods.
- Not linking the choice to the scenario (modules, uncertain requirements, safety).
- Leaving out the weakness of the chosen method.
- Stating agile has “no documentation” instead of less.
- Recap with the revision notes.
- Reread the study guide.
- Explore the Cambridge A Level IT hub and the printable 9626 checklist.
- Try all free 10-minute diagnostics.
- Book a free trial class.
Frequently asked questions
How do I pick a development method in an exam? Read the scenario for clues: fixed or changing requirements, modules, speed, user availability and safety. Match these to the method and justify it.
Do I need to know all five methods? Yes. The syllabus names agile, iterative, incremental, RAD and waterfall, with their stages and processes and their advantages and disadvantages.
Official syllabus
Cambridge International AS & A Level Information Technology 9626, syllabus for examination in 2025, 2026 and 2027, version 4, Cambridge University Press & Assessment. Section 16.8: Methods of software development.
Related resources
-
Revision notes
Cambridge A Level Information Technology (ICT): 16.8 Methods of software development (9626) – Revision Notes
Condensed revision notes on section 16.8 of Cambridge A Level IT 9626: waterfall, iterative, incremental, RAD and agile compared, with a self-test.
ICT · Cambridge · A Level
Revise topic -
Study guides
Cambridge A Level Information Technology (ICT): 16.1 The stages in the system life cycle (9626)
Study guide to section 16.1 of Cambridge A Level IT 9626: what a system is, the stages of developing one and how each stage feeds the next.
ICT · Cambridge · A Level
Read guide -
Practice questions
Cambridge A Level Information Technology (ICT): 16.1 The stages in the system life cycle (9626) – Practice Questions
Original practice questions with marked answers on systems and the stages of the system life cycle for section 16.1 of Cambridge A Level IT 9626.
ICT · Cambridge · A Level
Try questions
Get free revision emails (optional)
Occasional emails with practice questions, worked explanations and links to free resources for the qualification and subjects you choose. No spam, and you can unsubscribe from any email. The free tools on this site never need an email.