Cambridge IGCSE ICT (0417): Implementation – Practice Questions

Twelve original questions with answers on direct changeover, parallel, pilot and phased implementation in context, for Cambridge IGCSE ICT 0417 7.4.

Subject
ICT
Level
IGCSE
Topic
Topic 7: The systems life cycle
Updated

Aligned to Cambridge IGCSE ICT (0417), 2026-2028. Official specification .

Syllabus page (what it covers and how it is assessed): Cambridge IGCSE ICT.

Syllabus points this page covers

0417

  • 7.4 Implementation

Found an error? Report a correction.

Need help with this topic? Request a free trial class for IGCSE ICT (0417).

These questions cover section 7.4 “Implementation” of Cambridge IGCSE ICT 0417: the four methods of implementation, their characteristics, uses, advantages and disadvantages. All organisations are invented.

These are original questions written for Marlbridge, for revision and practice on this content. They are not reproduced past-paper questions, and they do not replicate the exam’s exact structure, question count or mark tariffs — Cambridge International holds copyright in its own papers. Use these alongside the official past papers available through your school or Cambridge directly.

Related: Implementation study guide · Implementation revision notes


Section A: short answers

1. Name the method of implementation in which the old system is stopped and the new system is started on the same day. [1]

2. Give two advantages of phased implementation. [2]

3. State one reason why parallel running is the most expensive method. [1]

4. Identify the method of implementation described in each case.

(a) A bank introduces its new system in its Northern region branches only, then the rest of the country. [1]

(b) A council introduces the new council-tax module first, then the parking-permits module, then the housing module. [1]

5. Give two reasons why direct changeover is risky. [2]


Section B: structured questions

6. Hilltop Veterinary Group has 18 surgeries. It is installing a new appointments and records system.

(a) Describe how pilot running would be carried out at Hilltop. [2]

(b) Give two advantages of pilot running for Hilltop. [2]

(c) Give one disadvantage of pilot running for Hilltop. [1]

7. Brookside Credit Union is replacing the system that records members’ savings and loans.

(a) Explain why parallel running would be suitable for Brookside. [3]

(b) Describe two problems Brookside’s staff might face during parallel running. [2]

8. Explain the difference between pilot running and phased implementation. [2]

9. A one-person dog-walking business is moving its bookings from a paper diary to a smartphone app. Explain why direct changeover is a suitable method. [3]

10. Marlowe Manufacturing’s new system has separate modules for stock control, production planning and payroll. Explain why phased implementation might suit this system. [3]

11. Compare direct changeover and parallel running for a hospital’s new patient records system. [6]

12. A school is replacing its electronic register and report system just before the summer holiday. Discuss which implementation method would be most suitable. [4]


Answers

1. Direct changeover [1]. [1]

2. Any two of: if one part fails only that part is affected [1]; problems are easy to trace to the part just introduced [1]; staff can learn the system one part at a time [1]; each part is checked before the next is added [1]. Maximum 2. [2]

3. Any one of: all work is done twice, in both systems [1]; extra staff time or overtime is needed [1]. Maximum 1. [1]

4. (a) Pilot running [1].

(b) Phased implementation [1]. [2]

5. Any two of: if the new system fails there is no old system to fall back on [1]; data could be lost [1]; work could stop completely [1]; all staff must be trained before the changeover, which may not be achieved [1]. Maximum 2. [2]

6. (a) The whole new system is introduced in one surgery first while the other 17 keep the old system [1]; once it works well there it is introduced in the remaining surgeries [1].

(b) Any two of: if the system fails, only one surgery’s appointments and records are affected [1]; faults can be fixed before the other surgeries change over [1]; staff at the pilot surgery can help train staff at other surgeries [1]; cheaper than running two systems at every surgery [1]. Maximum 2.

(c) Any one of: the other surgeries wait longer for the benefits [1]; the pilot surgery may not be typical, so some problems appear later [1]; if the pilot fails that surgery’s records may be affected [1]. Maximum 1. [5]

7. (a) Members’ savings and loans are financial records, so errors or lost data would be very serious [1]; with parallel running the old system is still running if the new one fails [1]; results from both systems can be compared, so errors in the new system are found before it is relied on [1].

(b) Any two of: every transaction must be entered twice, doubling the workload [1]; staff may make errors because they are tired or rushed [1]; overtime or extra temporary staff may be needed, increasing costs [1]; staff may be confused by using two systems at once [1]. Maximum 2. [5]

8. Pilot running introduces the whole new system at one site or department first [1], whereas phased implementation introduces one part of the system at a time across the whole organisation [1]. [2]

9. There is only one person and one location, so pilot or phased methods are not possible in a meaningful way [1]; direct changeover is the quickest and cheapest, which suits a very small business [1]; the risk is low because if the app fails the owner can return to the paper diary or contact customers directly [1]. [3]

10. The system is already divided into clear modules, so each can be introduced separately [1]; for example stock control can be introduced and checked before production planning [1]; if one module fails, the others are unaffected, and staff learn one module at a time [1]. [3]

11. Up to 6 marks for points about both methods, for example:

  • With direct changeover the new system is used at once, so benefits are immediate [1].
  • Direct changeover is cheaper because records are entered only once [1].
  • With direct changeover there is no fall-back, so if the new system fails patient records may be unavailable or lost [1].
  • With parallel running the old system is still available if the new one fails [1].
  • Parallel running allows outputs to be compared so errors are found before patients are affected [1].
  • Parallel running is expensive and doubles the work of busy staff [1].
  • Conclusion: parallel running is more suitable, because patient safety outweighs the extra cost [1]. Maximum 6; points about both methods are needed for full marks. [6]

12. Up to 4 marks, for example: during the holiday there are no pupils, so registers are not being taken [1]; this makes direct changeover more acceptable, because a failure would not affect daily registers and could be fixed before term [1]; parallel running would be less useful because there is little live data during the holiday to enter into both systems [1]; a reasoned conclusion, such as direct changeover in the holiday, with testing before the new term [1]. Credit any other method if it is justified with reference to the timing and the school. [4]

Frequently asked questions

Can two methods be combined? Yes. A common combination is pilot running with parallel running at the pilot site. If you combine methods, justify each part.

How many methods should I discuss in a “discuss” question? Enough to reach a justified conclusion: usually the method you recommend and at least one alternative you reject, with reasons.

Syllabus reference

Cambridge International, Cambridge IGCSE Information and Communication Technology (0417) syllabus for 2026, 2027 and 2028, Topic 7 “The systems life cycle”, section 7.4 “Implementation”.