Revision notes for Edexcel IAL Business 2.3.2: costs, forecasts, break-even, margin of safety, cash flow, budgets and variances, with a self-test.

Subject
Business
Level
AS LEVEL
Topic
Managing business activities
Updated

Aligned to Pearson Edexcel A Level Business (WBS12/01), Issue 1, September 2017. Official specification .

Syllabus page (what it covers and how it is assessed): Pearson Edexcel A Level Business.

Found an error? Report a correction.

Need help with this topic? Request a free trial class for A Level Business (YBS11).

Condensed recall for section 2.3.2 of Unit 2. For explanations and worked examples, use the Financial Planning study guide. Figures are invented.

Formula sheet

Sales revenue         = price x sales volume
Total costs           = fixed costs + variable costs
Variable costs        = variable cost per unit x output
Average cost          = total costs / output
Contribution per unit = selling price - variable cost per unit
Total contribution    = contribution per unit x units sold
Break-even output     = total fixed costs / contribution per unit
Margin of safety      = actual sales - break-even output
Profit                = total contribution - fixed costs
Net cash flow         = inflows - outflows
Closing balance       = opening balance + net cash flow

Costs at a glance

  • Fixed: do not vary with output in the short run (rent, salaries, insurance, loan interest).
  • Variable: vary directly with output (materials, packaging, piece-rate pay).
  • Average cost falls as output rises when fixed costs are spread over more units.
  • Improving sales: promotion, distribution, product improvement, new markets, price change matched to PED.
Pennant Print’s fixed costs of $18,000 stay the same while variable costs at $2.50 a unit rise from $15,000 at 6,000 units to $22,500 at 9,000. Total cost rises from $33,000 to $40,500, but average cost falls from $5.50 to $4.50.
Spreading the same fixed costs over more units lowers average cost.

Sales forecasting

Purpose Factors (specification) Difficulties
Plan production and inventory Consumer trends No history for new products or firms
Plan staffing Economic variables (incomes, inflation, interest and exchange rates) Tastes change quickly
Build cash-flow forecasts and budgets Actions of competitors Economy and rivals unpredictable
Support finance applications Owner optimism biases figures
Consumer trends, economic variables and competitors’ actions shape a sales forecast, which is used to plan production and inventory, staffing, cash-flow forecasts and budgets, and finance applications. Difficulties include no sales history, changing tastes, unpredictable economies and rivals, and owner optimism.
Every plan built on a forecast inherits its errors.

Break-even essentials

  • Break-even = no profit, no loss: total revenue = total costs.
  • Price up → contribution up → break-even down. Variable cost up → contribution down → break-even up. Fixed costs up → break-even up.
  • Always round break-even output up to the next whole unit.
  • Chart: fixed cost line flat; total cost starts at fixed cost; revenue starts at zero; crossing point = break-even; gap right of it = profit; distance from break-even to actual output = margin of safety.
  • Limitations: assumes all output sold; constant price and unit cost; fixed costs truly fixed; hard with many products; only as good as the forecast.
A break-even chart for Pennant Print with fixed costs of $18,000, total cost rising at $2.50 a unit and total revenue at $8.50 a unit. The lines cross at 3,000 units and $25,500. With expected sales of 4,200 units the margin of safety is 1,200 units.
Pennant breaks even at 3,000 units and expects a 1,200-unit margin of safety.
When Pennant’s variable cost rises from $2.50 to $3.50, the total cost line becomes steeper and break-even moves from 3,000 to 3,600 units. Against forecast sales of 4,200, the margin of safety halves from 1,200 to 600 units.
A $1 rise in unit cost halves Pennant’s margin of safety.
Two simple break-even charts. A price rise makes the total revenue line steeper, so break-even moves left. A rise in fixed costs shifts the total cost line up, so break-even moves right. Limitations: all output sold, constant price and unit cost, fixed costs at every output, many products and an uncertain forecast.
A steeper revenue line pulls break-even left; higher fixed costs push it right.

Cash flow essentials

  • Inflows: cash sales, receipts from credit customers, loans, owner capital, asset sales.
  • Outflows: suppliers, wages, rent, loan repayments, equipment, tax.
  • Credit sales arrive later than the sale, so growing firms can run short of cash.
  • Uses: spot shortfalls, arrange finance early, support a loan application, set targets.
  • Limitations: relies on forecasts; late payers; unexpected costs.
Holloway Tiles receives half of each month’s sales at once and half the next month, so inflows are $11,000, $13,500 and $16,500 for January to March. Against outflows of $12,500, $14,000 and $15,000, the closing balance falls from $4,000 to $2,500 and $2,000 before rising to $3,500.
Credit sales delay cash, so a growing business can still run short.

Budgets essentials

  • Purposes: set targets, control spending, allocate resources, measure performance.
  • Historical-figures budget: last year adjusted; quick but repeats inefficiency.
  • Zero-based budget: every item justified from zero; removes waste but slow.
  • Favourable variance: revenue above or cost below budget. Adverse: revenue below or cost above budget.
  • Difficulties: inaccurate forecasts, unrealistic targets, events overtaking the plan, time cost.
A waterfall from budgeted profit of $11,000 to actual profit of $7,300: revenue $4,000 adverse, materials $1,500 favourable, labour $1,200 adverse and overheads on budget, a total of $3,700 adverse.
Judge each variance by its effect on profit, then ask what caused it.

Linking the tools

Each tool feeds the next. The sales forecast sets expected volume; volume and costs give the break-even position and margin of safety; the same forecast, with credit terms and payment dates, builds the cash-flow forecast; and all of these become the budget, against which variances are measured. An error in the forecast therefore spreads into every other plan, which is the strongest evaluation point in this section.

Key terms

Term Meaning
Sales volume Number of units sold
Fixed costs Costs that do not change with output in the short run
Variable costs Costs that change directly with output
Contribution Selling price minus variable cost per unit, the amount each unit adds towards fixed costs and profit
Break-even point Output at which total revenue equals total costs
Margin of safety Amount by which sales exceed break-even output
Cash-flow forecast Prediction of cash inflows and outflows over future months
Zero-based budget A budget built from zero, with every item justified
Variance Difference between a budgeted and an actual figure
Adverse variance A difference that lowers profit compared with budget

Exam traps

  • Fixed costs ÷ contribution, never ÷ price.
  • A margin of safety can be stated in units or in revenue; give units unless asked otherwise.
  • Revenue is not cash if customers pay on credit.
  • A favourable cost variance may come from lower output, not efficiency.
  • A cash-flow forecast predicts; it does not show past results.
  • Do not call a negative closing balance a loss: it is a cash shortfall, which may be covered by an overdraft.

Self-test

  1. Fixed costs are $12,000; variable cost is $4 a unit; output is 2,000. Calculate total costs.
  2. Calculate average cost in question 1.
  3. Price is $10 and variable cost $4. Calculate contribution per unit.
  4. Using questions 1 and 3, calculate break-even output.
  5. Sales are 2,600 units. Calculate the margin of safety.
  6. State two purposes of a sales forecast.
  7. Name the three factors affecting sales forecasts in the specification.
  8. Opening balance $1,000; inflows $8,000; outflows $9,500. Calculate the closing balance.
  9. Give one limitation of a cash-flow forecast.
  10. Budgeted wages $15,000; actual $16,200. Calculate the variance and say whether it is adverse or favourable.
  11. Give one advantage of zero-based budgeting.
  12. What happens to the break-even point if the selling price falls?

Answers

  1. $12,000 + ($4 × 2,000) = $20,000.
  2. $20,000 ÷ 2,000 = $10 a unit.
  3. $10 − $4 = $6.
  4. $12,000 ÷ $6 = 2,000 units.
  5. 2,600 − 2,000 = 600 units.
  6. Any two: plan production and inventory, plan staffing, build cash-flow forecasts and budgets, support a finance application.
  7. Consumer trends, economic variables, actions of competitors.
  8. $1,000 + $8,000 − $9,500 = −$500 (a cash shortfall).
  9. Any one: it relies on forecasts that may be wrong; customers may pay late; unexpected costs are not included.
  10. $1,200 adverse, because the cost is above budget.
  11. Every cost must be justified, so wasteful spending carried over from previous years is removed.
  12. Contribution per unit falls, so the break-even point rises.