Revision notes on break-even analysis for OCR A Level Business H431: formulae, graph construction, effects of changes, stepped costs, special orders and a self-test.

Subject
Business
Level
A LEVELS
Topic
Accounting and financial considerations
Updated

Aligned to OCR A Level Business (H431), Version 2.1 (January 2026), for first assessment in 2017; final assessment summer 2027. Official specification .

Syllabus page (what it covers and how it is assessed): OCR A Level Business.

Syllabus points this page covers

H431

  • 6.5 Break-even analysis

Found an error? Report a correction.

Need help with this topic? Request a free trial class for A Level Business (H431).

Condensed notes on the Break-even analysis content (6.5 on this site) in the Area of Study Management accounting, OCR A Level Business H431, Version 2.1 (January 2026), final assessment summer 2027. Full explanations and five worked examples are in the break-even analysis study guide; test yourself with the break-even analysis practice questions. The whole topic is in the accounting and financial considerations revision notes.

What the specification lists

  • Explain break-even, contribution, margin of safety, target level of profit and a stepped fixed cost.
  • Construct and interpret a break-even graph.
  • Calculate and interpret contribution, break-even, margin of safety and target profit, and the effect of changes in costs and revenue.
  • Evaluate the impact of changes, and the impact and usefulness of break-even analysis.
  • Recommend and justify how to lower break-even.
  • Evaluate special order decisions.

Core recall

Formulae

Item Formula
Contribution per unit Price − variable cost per unit
Break-even output Fixed costs ÷ contribution per unit
Break-even revenue Break-even output × price
Margin of safety (units) Actual output − break-even output
Margin of safety (%) Margin of safety ÷ actual output × 100
Target output (Fixed costs + target profit) ÷ contribution per unit
Profit (Contribution per unit × output) − fixed costs

Round break-even output up to the next whole unit.

Constructing a graph

  1. Axes: output (horizontal), £ (vertical).
  2. Fixed cost line: horizontal.
  3. Total cost line: starts at fixed costs, rises by variable cost per unit.
  4. Total revenue line: starts at the origin, rises by price per unit.
  5. Mark break-even where revenue and total cost cross.
  6. Mark loss (left) and profit (right) areas, and the margin of safety.

Effects of changes

Change Break-even Margin of safety
Fixed costs rise Rises Falls
Variable cost rises Rises Falls
Price rises (demand holds) Falls Rises
Price falls Rises Falls
Output plan rises No change Rises

Stepped fixed cost

  • Fixed cost that stays constant over a range of output and then jumps to a higher level when capacity is passed.
  • The model is only valid within one step.

Special orders

  • Accept if: spare capacity, no extra fixed costs, price above variable cost (positive contribution), and no knock-on effect on regular prices.
  • Refuse or negotiate if: regular customers would demand the same price, or capacity could earn more elsewhere.
  • Short-run decision only.

Ways to lower break-even

Raise price, cut variable cost, cut fixed cost, change the product mix. Each has a risk to demand or quality.

Usefulness

  • Strengths: simple; shows risk; helps pricing and loan applications; “what if” tests.
  • Limits: one product, constant price and variable cost; assumes all output is sold; ignores stepped costs; depends on forecasts; says nothing about demand.

Quick worked reminder

Cobb Candles (invented): price £12, variable cost £5, fixed costs £42,000, planned sales 8,000. Contribution £7; break-even 6,000 candles (£72,000 revenue); margin of safety 2,000 (25%); profit £14,000; target profit £21,000 needs 9,000 candles. Fixed costs up to £49,000 give break-even 7,000. A special order of 1,500 candles at £8 adds 1,500 × £3 = £4,500 of contribution.

Exam prompts and how to approach them

  • “Calculate the margin of safety”: state break-even output, subtract it from actual output, and give the result in units and as a percentage.
  • “Evaluate a price rise using break-even”: show the new break-even, then test whether demand could fall enough to cancel the benefit.
  • “Evaluate a special order”: work out contribution, check spare capacity and fixed costs, and comment on the effect on regular prices.

Key terms

Term Meaning
Contribution Price minus variable cost per unit
Break-even point Output at which total revenue equals total cost
Margin of safety How far sales can fall before a loss is made
Target profit A planned profit used to find the output needed
Stepped fixed cost A fixed cost that jumps when capacity is exceeded
Special order A one-off order, often at a lower price
Total cost line Fixed plus variable costs at each output

Exam traps

  • Divide fixed costs by contribution, not by price.
  • The total cost line starts at the fixed cost level.
  • Rounding: break-even is rounded up.
  • A margin of safety is relative to actual or planned output, not to break-even.
  • A special order is judged on contribution, with a comment on the regular price.

Self-test

  1. Define contribution per unit.
  2. Price £25, variable cost £10, fixed costs £60,000. Calculate break-even output.
  3. Calculate break-even revenue.
  4. Planned output is 5,000. Calculate the margin of safety in units and as a percentage.
  5. Calculate the profit at 5,000 units.
  6. Calculate the output needed for a profit of £30,000.
  7. Fixed costs rise to £66,000. State the new break-even output.
  8. Name one effect of a price rise on break-even.
  9. What is a stepped fixed cost?
  10. 600 units are offered at £16 each. Calculate the contribution from the order.
  11. Give one condition for accepting a special order.
  12. Give one limitation of break-even analysis.

Answers

  1. Price minus variable cost per unit.
  2. Contribution £15; £60,000 ÷ £15 = 4,000 units.
  3. 4,000 × £25 = £100,000.
  4. 5,000 − 4,000 = 1,000 units; 1,000 ÷ 5,000 × 100 = 20%.
  5. (£15 × 5,000) − £60,000 = £15,000.
  6. (£60,000 + £30,000) ÷ £15 = 6,000 units.
  7. £66,000 ÷ £15 = 4,400 units.
  8. It raises the contribution, so break-even output falls (if demand holds).
  9. A fixed cost that stays constant up to a level of output and then jumps to a higher level.
  10. £16 − £10 = £6 per unit; 600 × £6 = £3,600.
  11. Any one: spare capacity; no rise in fixed costs; no effect on regular prices; positive contribution.
  12. Any one: assumes all output is sold; assumes constant price and variable cost; ignores demand.

Official syllabus

OCR, Advanced GCE in Business (H431), specification Version 2.1 (January 2026): Area of Study Management accounting, content Break-even analysis.

Related resources

Get free revision emails (optional)

Occasional emails with practice questions, worked explanations and links to free resources for the qualification and subjects you choose. No spam, and you can unsubscribe from any email. The free tools on this site never need an email.