A Level Business: Operations Management — Practice Questions (Cambridge 9609)

Original exam-style practice questions with full worked answers on inventory management, re-order levels, buffer inventory, just-in-time, capacity utilisation and productivity for Cambridge AS & A Level Business (9609) Topic 4.

Subject
Business
Level
AS LEVEL
Topic
Operations management
Updated

Aligned to Cambridge A Level Business (9609), For examination in 2026, 2027 and 2028. Official specification .

Syllabus page (what it covers and how it is assessed): Cambridge A Level Business.

Syllabus points this page covers

9609 (AS Level)

  • 4 Operations management (whole topic)

Found an error? Report a correction.

Need help with this topic? Request a free trial class for A Level Business (9609).

These are original questions written for Marlbridge, for revision and practice on this content. They are not reproduced past-paper questions, and they do not replicate the exam’s exact structure, question count or mark tariffs — Cambridge International holds copyright in its own papers. Use these alongside the official past papers available from your board.


Questions

1. Define the term re-order level, and explain how it differs from buffer inventory. [2]

2. A shop uses 50 units a day. The supplier’s lead time is 6 days and the shop keeps a buffer inventory of 100 units. Calculate the re-order level. [2]

3. State one advantage and one disadvantage to a business of just-in-time (JIT) inventory management. [2]

4. A factory produces 3600 units a month. Its maximum capacity is 4500 units a month. Calculate its capacity utilisation. [2]

5. Define labour productivity and give one way a business could increase it. [2]

Answers

1. The re-order level is the level of inventory at which a new order is placed with the supplier [1]; it is set so the delivery arrives before inventory falls below the buffer inventory, the minimum safety level kept to cover unexpected demand or late deliveries [1].

Examiner insight (June 2025): weaker answers confused the re-order level with just-in-time inventory management and wrote about low inventory holding costs. The re-order level belongs to a traditional inventory system that holds buffer inventory. Try the real question next: Cambridge International AS & A Level Business 9609, June 2025, Paper 12, Question 3.

2. Usage during the lead time = 50 × 6 = 300 units [1]; re-order level = 300 + 100 = 400 units [1].

3. Advantage: lower inventory holding costs (less storage space, less waste) [1]. Disadvantage: production can stop if a supplier delivers late, because there is no buffer inventory [1].

4. 3600 ÷ 4500 × 100 [1] = 80% [1].

5. Output per worker in a given period [1]; for example, training, better equipment or improved motivation [1].


Where marks are usually lost

  • Confusing the re-order level with JIT.
  • Forgetting to add the buffer inventory when calculating the re-order level.
  • Calculating capacity utilisation the wrong way round.

Get free revision emails (optional)

Occasional emails with practice questions, worked explanations and links to free resources for the qualification and subjects you choose. No spam, and you can unsubscribe from any email. The free tools on this site never need an email.

Subjects (optional, up to 6)

Choose a qualification to see its subjects.

Related resources

Related articles

Studying this with a teacher

Working through Business AS LEVEL?

This page is free and stays free. If you would rather be taught it, Marlbridge runs Business classes one-to-one and in small groups of up to 15, online in your own time zone. The first trial class is free. WhatsApp replies within an hour (8am–11pm Pakistan time, every day); email the same day.