Practice Questions
Edexcel International A Level Law (YLA1): Discharge of Contract: Performance, Agreement, Breach and Frustration – Practice Questions
Original practice questions with full answers on discharge by performance, agreement, breach and frustration, and the 1943 Act (YLA1 content area 2.1.4).
- Subject
- Law
- Level
- A LEVELS
- Topic
- Paper 2 – The Law in Action
- Author
- Marlbridge Academic Team
- Updated
- Reviewed by
- Aizaz Raoof Ali (what this means)
Aligned to Pearson Edexcel A Level Law (YLA1), Issue 4, November 2021. Official specification .
Syllabus page (what it covers and how it is assessed): Pearson Edexcel A Level Law.
Syllabus points this page covers
YLA1
- 2.1 The market
Found an error? Report a correction.
Need help with this topic? Request a free trial class for A Level Law (YLA1).
These are original questions written for Marlbridge, for revision and practice on this content. They are not reproduced past-paper questions, and they do not replicate the exam’s exact structure, question count or mark tariffs — examination boards hold copyright in their own papers. Use these alongside the official past papers available free from your board.
Related: Discharge of contract study guide · Discharge of contract revision notes · Market practice questions
These questions cover the discharge bullet of content area 2.1.4: performance, agreement, breach and frustration, including the Law Reform (Frustrated Contracts) Act 1943. The market practice page has a further question on a frustrated booking.
Section A
1. State the general rule on discharge by performance, using one decided case. [2]
2. Explain the doctrine of substantial performance, using two decided cases. [4]
3. Explain the difference between bilateral and unilateral discharge by agreement. [3]
4. Identify three situations in which a contract will not be frustrated even though performance has become harder. [3]
5. State what section 1(3) of the Law Reform (Frustrated Contracts) Act 1943 provides. [2]
Section B
6. Chen agrees to tile Mira’s bathroom for £2,400, payable on completion. He tiles the whole room but several tiles are cracked; replacing them would cost £150. Mira refuses to pay anything.
Advise Chen. [4]
7. In March, Hollis Ltd agrees to supply 500 chairs to a hotel on 1 September. In May, Hollis writes to say it will not deliver.
Explain the options open to the hotel, using decided cases. [6]
8. Omar charters a ship for two years. During the first year the ship is out of service for five weeks because the crew are inexperienced. Omar wants to end the charter.
Explain whether Omar may treat the contract as ended. [4]
9. Ayesha, a famous violinist, contracts to perform at a festival. A month before, she breaks her wrist and cannot play for six months. The organisers had paid her a £5,000 advance; she had spent £600 on travel arrangements.
(a) Explain whether the contract is frustrated. [3]
(b) Explain how the 1943 Act deals with the advance and her expenses. [3]
10. A shipping company has two vessels and three contracts. One vessel sinks, and the company chooses to use the other for two of the contracts, cancelling the third.
Explain whether the third contract is frustrated. [3]
11. Explain, using decided cases, the difference between Krell v Henry and Herne Bay Steam Boat v Hutton. [4]
12. Evaluate whether the doctrine of frustration and the Law Reform (Frustrated Contracts) Act 1943 deal fairly with unforeseen events. [12]
Answers
1. Performance must be complete and exact to discharge the contract [1]: in Cutter v Powell (1795) a sailor who died before the end of the voyage earned nothing under a lump-sum contract [1].
2. Where a party has substantially performed, they may recover the contract price less the cost of remedying defects [1]. In Hoenig v Isaacs [1952] decorating with minor defects was substantial performance, so the price was payable less repair costs [1]. The doctrine does not apply where defects are serious [1]: in Bolton v Mahadeva [1972] a heating system that gave off fumes and heated poorly was not substantially performed, so nothing was payable [1].
3. In bilateral discharge both parties still have obligations, so each gives up rights, which is consideration on both sides [1]. In unilateral discharge one party has already performed [1], so a release by that party needs new consideration (accord and satisfaction) or a deed [1].
4. Any three [1] each: performance is merely more expensive or difficult (Davis Contractors; Tsakiroglou); the purpose is only partly defeated (Herne Bay); the event is self-induced (Maritime National Fish; Super Servant Two); the event was foreseen or provided for by a force majeure clause.
5. Where a party has obtained a valuable benefit other than money before the frustrating event [1], the court may order them to pay a just sum for it (BP Exploration v Hunt) [1].
6. Strictly, payment is due only on complete performance (Cutter v Powell) [1]. But Chen has substantially performed: the job is done and the defects are minor compared with the price [1], as in Hoenig v Isaacs [1952] [1]. He can recover £2,400 less £150, that is £2,250 [1].
7. Hollis has committed an anticipatory breach [1]. The hotel may accept the breach and sue immediately for damages (Hochster v De La Tour (1853)) [1], and should then mitigate by buying chairs elsewhere [1]. Alternatively it may affirm the contract and wait until 1 September [1], but it then takes the risk of later events, as in Avery v Bowden (1855), where the outbreak of war frustrated the contract and the right to sue was lost [1]. If it keeps the contract alive it may in some cases perform and claim the price only where it has a legitimate interest (White and Carter v McGregor [1962]) [1].
8. The term that the ship is seaworthy and properly crewed is likely an innominate term [1]. Under Hong Kong Fir Shipping [1962] the innocent party may end the contract only if the breach deprives them of substantially the whole benefit of the contract [1]. Five weeks out of two years is a small part of the charter [1], so Omar can claim damages but probably cannot treat the contract as ended [1].
9. (a) The contract is personal: only Ayesha can perform it [1]. Her injury, which is no one’s fault and occurred after formation [1], makes performance impossible on the date, as in Robinson v Davison (1871), so the contract is frustrated [1].
(b) Under s 1(2) the £5,000 advance is recoverable by the organisers [1]. The court may allow Ayesha to keep up to £600 for expenses incurred in performing [1], if it considers this just; it is not bound to, as Gamerco v ICM [1995] shows [1].
10. Frustration cannot be self-induced [1]. The company chose which contract to cancel, so the failure to perform the third contract results from its own decision rather than from the sinking alone [1]. As in The Super Servant Two [1990], the third contract is not frustrated and the company is liable for breach [1].
11. In Krell v Henry [1903] rooms were hired solely to watch the coronation procession [1]; when it was cancelled the whole purpose of the contract was defeated, so it was frustrated [1]. In Herne Bay Steam Boat v Hutton [1903] a boat was hired to watch the naval review and cruise round the fleet [1]; when the review was cancelled the cruise was still possible, so the purpose was only partly defeated and the contract was not frustrated [1].
12. Levels-based answer. Credit:
- AO1: the test (Taylor v Caldwell; Davis Contractors); categories; limits (self-induced, more expensive, foreseen); the 1943 Act, s 1(2) and s 1(3), with Gamerco and BP v Hunt.
- Fairness: frustration releases parties from obligations they could not perform through no fault of their own; the Act prevents a party keeping advance payments (reversing the harshness before Fibrosa); the court’s discretion over expenses lets loss be shared.
- Criticisms: the doctrine is narrow, so parties bear the risk of much hardship (Tsakiroglou); the line between frustration and mere difficulty is uncertain (Krell versus Herne Bay); the expenses discretion makes results unpredictable; the Act does not apply to some contracts, such as many insurance contracts.
- Evaluation: reach a conclusion, for example that the combination works fairly because businesses can draft force majeure clauses, while the law supplies a fallback for truly unforeseen events.
Top-level answers apply cases accurately and reach a justified conclusion.
Where marks are usually lost
- Calling a contract frustrated because it became more expensive.
- Treating every breach as allowing the contract to be ended.
- Forgetting the risks of waiting after an anticipatory breach.
- Ignoring self-induced frustration.
- Saying the payee always keeps expenses under the 1943 Act.
Related resources
-
Revision notes
Edexcel International A Level Law (YLA1): Discharge of Contract: Performance, Agreement, Breach and Frustration – Revision Notes
Condensed notes on discharge by performance, agreement, breach and frustration, the 1943 Act, leading cases, traps and a self-test, for YLA1 content area 2.1.4.
Law · Pearson Edexcel · A Level
Revise topic -
Study guides
Edexcel International A Level Law (YLA1): General Defences: Duress and Intoxication
Duress of threats and of circumstances, and voluntary and involuntary intoxication, step by step with cases and a worked scenario, for YLA1 2.2.8 and 2.2.9.
Law · Pearson Edexcel · A Level
Read guide -
Practice questions
Edexcel International A Level Law (YLA1): General Defences: Duress and Intoxication – Practice Questions
Original practice questions with full answers on duress of threats, duress of circumstances, and voluntary and involuntary intoxication (YLA1 2.2.8 and 2.2.9).